UPSC Prelims 2021 CSAT Paper II · Q80 / 79 Basic Numeracy easy

A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work is further increased by 50% ?

  1. (a) 24
  2. (b) 21
  3. (c) 18
  4. (d) 15 ✓ UPSC's answer

Why the answer is (d)

• The man completes 7/8 of a job in 21 days, so his rate of work is (7/8) ÷ 21 = 1/24 of the job per day.

• The quantum of work is increased by 50%, making the total work 1.5 times the original, but he has already completed 7/8 of the original job.

• The remaining work to be done is 1.5 - 7/8 = 12/8 - 7/8 = 5/8 of the original job.

• At his rate of 1/24 of the job per day, the time required to complete 5/8 of the job is (5/8) ÷ (1/24) = (5/8) × 24 = 15 days.

• Therefore, it will take him 15 more days to finish the job, so the answer is option (d).

Why the other options are wrong

(a) 24
This option incorrectly calculates the remaining work or applies the wrong rate, resulting in an inflated number of days.
(b) 21
This option appears to assume he continues at the same pace for the same duration as the first 7/8, ignoring that the remaining work after the 50% increase is only 5/8 of the original job.
(c) 18
This option miscalculates the remaining work after the 50% increase, likely treating it as 3/4 instead of 5/8 of the original job.

Asked in the CSAT Paper II of the UPSC Civil Services Preliminary Examination 2021, held on 10 October 2021. Question and answer key: Union Public Service Commission. Explanation: UPSC Answer Check.

Reading the answer is not the same as getting it right under a clock. Practise this question with UPSC's negative marking, and anything you miss goes into an error notebook until you get it right twice.

Practise this paper free

Practise Prelims PYQs and the daily 21 free

Score the daily set, see your rank, and let Guru explain what you missed.

Start free

Already have an account? Log in