Civil Engineering 2023 Paper II 50 marks Compulsory Calculate

Paper II — Q5

(a) A 6-hour unit hydrograph has the following ordinates (time in hr : ordinate in m³/s): 0 : 0; 6 : 200; 12 : 550; 18 : 750; 24…

(a)

A 6-hour unit hydrograph has the following ordinates (time in hr : ordinate in m³/s): 0 : 0; 6 : 200; 12 : 550; 18 : 750; 24 : 650; 30 : 550; 36 : 400; 42 : 270; 48 : 150; 54 : 50; 60 : 0. If φ index is 0.3 cm/hr and base flow is 25 m³/s, determine the ordinates of resulting hydrograph of flow in the catchment due to the storm given below (time from start of storm in hr : accumulated rainfall in cm): 0 : 0; 6 : 3; 12 : 8; 18 : 12. 10 marks

(b)
(i)

The annual precipitation and evaporation from each of the sub-areas P, Q, R and S are given below for a catchment (sub-area : area in km², annual precipitation in mm, annual evaporation in mm): P : 15, 1000, 500; Q : 5, 800, 400; R : 10, 900, 440; S : 18, 1200, 650. Calculate the following for catchment : Annual average precipitation

(ii)

Annual average evaporation

(iii)

Annual runoff coefficients for the sub-areas and for the total catchment taken as a whole assuming no change in the ground water storage on an annual basis. 10 marks

(c)

Route the above flood hydrograph through a river reach (time in hr : inflow in m³/s): 0 : 10; 4 : 20; 8 : 30; 12 : 30; 16 : 25; 20 : 20; 24 : 35; 28 : 12. The value of x and K in the Muskingham equation have been identified as 0.25 and 8 hr. The initial outflow discharge from the reach is 10 m³/s. 10 marks

(d)

Explain the significance of the following from the point of view of water quality criteria : (i) Nitrites (ii) Nitrates (iii) E-coli (iv) B.O.D. (v) Dissolved oxygen 10 marks

(e)

In a continuous flow settling tank 4 m deep and 80 m long, calculate the flow velocity for effective removal of 0.03 mm particles at 25°C. The specific gravity of the particles is 2.65 and kinematic viscosity (v) for water may be taken as 0.01 cm²/sec. 10 marks

हिंदी में प्रश्न पढ़ें

(क) एक 6-घंटा एकांक जललेख की निम्नलिखित कोटियाँ हैं (समय घंटा : कोटि m³/s): 0 : 0; 6 : 200; 12 : 550; 18 : 750; 24 : 650; 30 : 550; 36 : 400; 42 : 270; 48 : 150; 54 : 50; 60 : 0 । यदि φ सूचकांक 0.3 cm/hr एवं आधार प्रवाह 25 m³/s है, तो नीचे दिए गए वृष्टि (वृष्टि के आरंभ से समय घंटा : संचित वर्षा cm: 0 : 0; 6 : 3; 12 : 8; 18 : 12) के कारण अपवाह क्षेत्र में उत्पन्न होने वाले प्रवाह के जललेख की कोटियों को निर्धारित कीजिए । (10 अंक)

(i)

(ख) एक अपवाह क्षेत्र के सभी उपक्षेत्रों P, Q, R एवं S के वार्षिक वृष्टिपात और वाष्पीकरण नीचे दिए गए हैं (उपक्षेत्र : क्षेत्रफल km², वार्षिक वृष्टिपात mm, वार्षिक वाष्पीकरण mm): P : 15, 1000, 500; Q : 5, 800, 400; R : 10, 900, 440; S : 18, 1200, 650 । अपवाह क्षेत्र के लिए निम्नलिखित की गणना कीजिए : वार्षिक औसत वृष्टिपात

(ii)

वार्षिक औसत वाष्पीकरण

(iii)

वार्षिक अपवाह गुणांक, सभी उपक्षेत्रों के लिए और संपूर्ण सकल अपवाह क्षेत्र के लिए यह मानते हुए कि वार्षिक आधार पर भौम जल संचयन में कोई परिवर्तन नहीं है । (10 अंक)

(ग) नदी के एक खंड के लिए निम्नलिखित बाढ़ जलालेख का मार्गाभिगमन कीजिए (समय घंटा : अंतर्वाह m³/s): 0 : 10; 4 : 20; 8 : 30; 12 : 30; 16 : 25; 20 : 20; 24 : 35; 28 : 12 । मस्किंघम समीकरण में प्रयुक्त होने वाले x एवं K का मान 0.25 एवं 8 घंटे हैं । नदी खंड से होने वाला प्रारम्भिक बहिर्प्रवाह निस्सरण 10 m³/s है । (10 अंक)

(घ) जल की गुणवत्ता की कसौटी की दृष्टि से निम्नलिखित की सार्थकता की व्याख्या कीजिए : (i) नाइट्राइट (ii) नाइट्रेट (iii) ई-कोलाई (iv) बी.ओ.डी. (v) घुलित ऑक्सीजन (10 अंक)

(ङ) एक निरंतर प्रवाह अवसाद टंकी जो कि 80 m लम्बी एवं 4 m गहरी है, उसमें 25°C पर 0.03 mm के कणों को प्रभावी रूप से हटाने के लिए प्रवाह गति ज्ञात कीजिए । कणों का विशिष्ट घनत्व 2.65 है और जल की शुद्धगतिक श्यानता (v) को 0.01 cm²/sec लिया जा सकता है । (10 अंक)

Q5 of the 2023 UPSC Mains Civil Engineering Paper II, as printed
The question as printed in the 2023 Civil Engineering paper

The figure this question refers to, in words

The question paper is a scan and the diagram did not survive as text. This is the figure as read from the original page — every component, value and label — so the question can be worked from the text below.

(a) Table 2: Storm data. Row 1 (Time from start of storm (hr)): 0, 6, 12, 18. Row 2 (Accumulated rainfall (cm)): 0, 3, 8, 12.

(b) Table with columns: Sub-area, Area (km2), Annual Precipitation (mm), Annual Evaporation (mm). Rows: P, 15, 1000, 500; Q, 5, 800, 400; R, 10, 900, 440; S, 18, 1200, 650.

(c) Table with two rows. Row 1 (Time (hr)): 0, 4, 8, 12, 16, 20, 24, 28. Row 2 (Inflow (m3/s)): 10, 20, 30, 30, 25, 20, 35, 12.

Model answer

Drafted with AI by UPSC Answer Check against this question's marking rubric, to the expected length. UPSC does not publish answers for Mains — this is one way to score well, not an official key. How we build rubrics and answers.

(a) Resulting flood hydrograph

Incremental rainfall in each 6 h: 3, 5 and 4 cm. The φ index removes 0.3 × 6 = 1.8 cm in each interval, so the effective rainfall is 1.2, 3.2 and 2.2 cm.

The direct runoff is the superposition of the 6-h unit hydrograph, scaled by 1.2, 3.2 and 2.2 and lagged by 0, 6 and 12 h: DRH(t) = 1.2 U(t) + 3.2 U(t − 6) + 2.2 U(t − 12). For example, at 24 h: 1.2 × 650 + 3.2 × 750 + 2.2 × 550 = 780 + 2400 + 1210 = 4390 m³/s.

Adding the base flow of 25 m³/s gives the ordinates (time in h: flow in m³/s): 0: 25; 6: 265; 12: 1325; 18: 3125; 24: 4415; 30: 4415; 36: 3695; 42: 2839; 48: 1949; 54: 1159; 60: 515; 66: 135; 72: 25.

The peak is 4415 m³/s from 24 to 30 h. As a check, the DRH volume is 509 × 10⁶ m³, which equals 6.6 cm of effective rain on the 7710 km² catchment implied by the unit hydrograph.

(b) Catchment water balance

Total area = 15 + 5 + 10 + 18 = 48 km².

(i) Average precipitation = (15 × 1000 + 5 × 800 + 10 × 900 + 18 × 1200)/48 = 49 600/48 = 1033.3 mm.

(ii) Average evaporation = (15 × 500 + 5 × 400 + 10 × 440 + 18 × 650)/48 = 25 600/48 = 533.3 mm.

(iii) With no change in groundwater storage, runoff = P − E. Sub-area runoff: P 500 mm, Q 400 mm, R 460 mm, S 550 mm. Runoff coefficients = runoff/precipitation: P = 0.50, Q = 0.50, R = 460/900 = 0.51, S = 550/1200 = 0.46. For the whole catchment, runoff = 1033.3 − 533.3 = 500 mm, so the coefficient = 500/1033.3 = 0.48.

(c) Muskingum routing

Δt = 4 h, K = 8 h, x = 0.25. C₀ = (0.5Δt − Kx)/(K − Kx + 0.5Δt) = (2 − 2)/8 = 0. C₁ = (0.5Δt + Kx)/8 = 4/8 = 0.5. C₂ = (K − Kx − 0.5Δt)/8 = 4/8 = 0.5. The sum is 1.

O₂ = C₀I₂ + C₁I₁ + C₂O₁, which here is O(t + 4) = 0.5 I(t) + 0.5 O(t).

Outflow (time in h: m³/s): 0: 10; 4: 0.5 × 10 + 0.5 × 10 = 10; 8: 0.5 × 20 + 0.5 × 10 = 15; 12: 0.5 × 30 + 0.5 × 15 = 22.5; 16: 0.5 × 30 + 0.5 × 22.5 = 26.25; 20: 0.5 × 25 + 0.5 × 26.25 = 25.63; 24: 0.5 × 20 + 0.5 × 25.63 = 22.81; 28: 0.5 × 35 + 0.5 × 22.81 = 28.91.

The outflow peak of 26.25 m³/s is lower and later than the inflow peak of 30 m³/s, showing attenuation and lag in the reach.

(d) Water quality indicators

Nitrite is an intermediate of nitrification; its presence shows recent, incomplete oxidation of organic or ammoniacal pollution and it is toxic (methaemoglobinaemia in infants), so it should be very low. Nitrate is the end product of nitrification; it shows older pollution or fertiliser and sewage input, promotes eutrophication and causes blue-baby syndrome; the BIS limit is 45 mg/L. E. coli is the indicator of faecal contamination and of possible pathogens, so it should be absent in 100 mL of drinking water. BOD measures the biodegradable organic load as the oxygen bacteria need in 5 days at 20°C; a high BOD means heavy pollution and oxygen depletion. Dissolved oxygen is needed by aquatic life; low DO (below about 4–5 mg/L) indicates pollution and stress, and DO together with BOD describes the health of a stream.

(e) Settling tank velocity

The settling velocity by Stokes' law is v_s = g(G − 1)d²/(18ν) = 981 × 1.65 × (0.003)²/(18 × 0.01) = 0.081 cm/s. Re = v_s d/ν = 0.024, below 1, so Stokes' law is valid.

For removal of all such particles, the particle must settle the depth H while travelling the length L, so v_s/v = H/L. The flow velocity v = v_s L/H = 0.081 × 80/4 = 1.62 cm/s (about 0.016 m/s), which is the maximum allowed.

How this answer will be evaluated

What earns full marks: All parts solved with correct methods, clear steps, and proper units.

Evaluation rubric

Each sub-part is marked on its own, against the marks and word limit printed on the paper.

  1. (a) Find the ordinates of the resulting flood hydrograph for the given storm, φ index and base flow. 10 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Incremental rainfall 3, 5 and 4 cm; φ loss 1.8 cm per 6 h
    • Effective rainfall 1.2, 3.2 and 2.2 cm
    • DRH = 1.2U(t) + 3.2U(t − 6) + 2.2U(t − 12)
    • Add base flow 25 m³/s; peak 4415 m³/s

    Loses marks

    • Subtracting φ from cumulative rainfall instead of each interval.

    Earns more

    • Marks for effective rainfall, superposition, base flow and peak.

    Extra mark

    • Checking the DRH volume against the effective rainfall.
  2. (b) Find the average precipitation, average evaporation and runoff coefficients. 10 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Area-weighted P = 1033.3 mm
    • Area-weighted E = 533.3 mm
    • Runoff = P − E: 500, 400, 460 and 550 mm for the sub-areas
    • Runoff coefficients 0.50, 0.50, 0.51, 0.46; catchment 0.48

    Loses marks

    • Using an arithmetic mean of the four sub-areas.

    Earns more

    • Marks for weighted averages and each coefficient.

    Extra mark

    • Stating the zero storage change assumption.
  3. (c) Route the given inflow hydrograph by the Muskingum method. 10 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Δt = 4 h, C₀ = 0, C₁ = 0.5, C₂ = 0.5
    • O(t + Δt) = C₀I₂ + C₁I₁ + C₂O₁
    • Outflows 10, 10, 15, 22.5, 26.25, 25.63, 22.81, 28.91
    • Attenuation and lag of the outflow peak

    Loses marks

    • Using an inconsistent time step.

    Earns more

    • Marks for the coefficients and the routed outflows.

    Extra mark

    • Commenting on attenuation and lag.
  4. (d) Explain the significance of nitrites, nitrates, E. coli, BOD and dissolved oxygen in water quality. 10 marks

    explain— definition/context → points in order → small example → short close

    Must cover

    • Nitrite: recent pollution and toxicity
    • Nitrate: end product; eutrophication and blue-baby syndrome
    • E. coli: faecal contamination indicator
    • BOD and DO: organic load and aquatic life support

    Loses marks

    • Defining the terms without explaining their significance.

    Earns more

    • Marks for the significance of each indicator.

    Extra mark

    • Quoting standard limits such as 45 mg/L nitrate.
  5. (e) Find the flow velocity in the settling tank for removal of 0.03 mm particles. 10 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Stokes' law v_s = g(G − 1)d²/(18ν) = 0.081 cm/s
    • Check Re < 1
    • v_s/v = H/L
    • v = 0.081 × 80/4 = 1.62 cm/s

    Loses marks

    • Using particle diameter in mm in the formula.

    Earns more

    • Marks for the settling velocity, the Reynolds check and the flow velocity.

    Extra mark

    • Converting to m/s.
What "Calculate" is asking you to do

Apply the standard formula or schedule to data the question has already supplied — a table of readings, cost records, a balance sheet — and produce the number. The method is rarely in doubt; the marks sit in the named intermediate quantities, each of which has to appear as a labelled line.

Structure that answers it

Data as given → formula or standard treatment, named → substitution → each intermediate, labelled → result with units

Where marks are lost

Omitting an intermediate the marking scheme pays for separately, or rounding at an intermediate line so the final figure drifts. In commerce and accountancy, any figure in a statement that no numbered working note supports is treated as unearned.

All UPSC directive words, compared →

Practice this exact question

Write your answer and it is marked point by point against the model answer above — what you covered, what you missed, what you got wrong.

Evaluate my answer →

More from Civil Engineering 2023 Paper II

Write this answer and get it marked in about 20 seconds

Free account: 5 AI evaluations a month, marked against the rubric above.

Start free

Already have an account? Log in