Civil Engineering 2023 Paper II 50 marks Compulsory Calculate

Paper II — Q5

(a) A 6-hour unit hydrograph has the following ordinates : If φ index is 0·3 cm/hr and base flow is 25 m³/s, determine the…

(a)

A 6-hour unit hydrograph has the following ordinates : If φ index is 0·3 cm/hr and base flow is 25 m³/s, determine the ordinates of resulting hydrograph of flow in the catchment due to the storm given below : 10 marks

(b)

The annual precipitation and evaporation from each of the sub-areas P, Q, R and S are given below for a catchment. Calculate the following for catchment : (i) Annual average precipitation (ii) Annual average evaporation (iii) Annual runoff coefficients for the sub-areas and for the total catchment taken as a whole assuming no change in the ground water storage on an annual basis. 10 marks

(c)

Route the above flood hydrograph through a river reach : The value of x and K in the Muskingham equation have been identified as 0·25 and 8 hr. The initial outflow discharge from the reach is 10 m³/s. 10 marks

(d)

Explain the significance of the following from the point of view of water quality criteria : (i) Nitrites (ii) Nitrates (iii) E-coli (iv) B.O.D. (v) Dissolved oxygen 10 marks

(e)

In a continuous flow settling tank 4 m deep and 80 m long, calculate the flow velocity for effective removal of 0.03 mm particles at 25°C. The specific gravity of the particles is 2.65 and kinematic viscosity (v) for water may be taken as 0.01 cm²/sec. 10 marks

हिंदी में प्रश्न पढ़ें
(a)

एक 6-घंटा एकांक जललेख की निम्नलिखित कोटियाँ हैं । यदि φ सूचकांक 0·3 cm/hr एवं आधार प्रवाह 25 m³/s है, तो नीचे दिए गए वृष्टि के कारण अपवाह क्षेत्र में उत्पन्न होने वाले प्रवाह के जललेख की कोटियों को निर्धारित कीजिए । 10 marks

(b)

एक अपवाह क्षेत्र के सभी उपक्षेत्रों P, Q, R एवं S के वार्षिक वृष्टिपात और वाष्पीकरण नीचे दिए गए हैं । अपवाह क्षेत्र के लिए निम्नलिखित की गणना कीजिए : (i) वार्षिक औसत वृष्टिपात (ii) वार्षिक औसत वाष्पीकरण (iii) वार्षिक अपवाह गुणांक, सभी उपक्षेत्रों के लिए और संपूर्ण सकल अपवाह क्षेत्र के लिए यह मानते हुए कि वार्षिक आधार पर भौम जल संचयन में कोई परिवर्तन नहीं है । 10 marks

(c)

नदी के एक खंड के लिए निम्नलिखित बाढ़ जलालेख का मार्गणिमगम कीजिए । मस्किंघम समीकरण में प्रयुक्त होने वाले x एवं K का मान 0·25 एवं 8 घंटे हैं । नदी खंड से होने वाला प्रारंभिक बहिर्वाह निस्सरण 10 m³/s है । 10 marks

(d)

जल की गुणवत्ता की कसौटी की दृष्टि से निम्नलिखित की सार्थकता की व्याख्या कीजिए : (i) नाइट्राइट (ii) नाइट्रेट (iii) ई-कोलाई (iv) बी.ओ.डी. (v) घुलीत ऑक्सीजन 10 marks

(e)

एक निरंतर प्रवाह अवसाद टंकी जो कि 80 m लंबी एवं 4 m गहरी है, उसमें 25°C पर 0.03 mm के कणों को प्रभावी रूप से हटाने के लिए प्रवाह गति ज्ञात कीजिए । कणों का विशिष्ट घनत्व 2.65 है और जल की शुद्धगतिक श्यानता (v) को 0.01 cm²/sec लिया जा सकता है । 10 marks

Q5 of the 2023 UPSC Mains Civil Engineering Paper II, as printed
The question as printed in the 2023 Civil Engineering paper

The figure this question refers to, in words

The question paper is a scan and the diagram did not survive as text. This is the figure as read from the original page — every component, value and label — so the question can be worked from the text below.

(a) Table 2: Storm data. Row 1 (Time from start of storm (hr)): 0, 6, 12, 18. Row 2 (Accumulated rainfall (cm)): 0, 3, 8, 12.

(b) Table with columns: Sub-area, Area (km2), Annual Precipitation (mm), Annual Evaporation (mm). Rows: P, 15, 1000, 500; Q, 5, 800, 400; R, 10, 900, 440; S, 18, 1200, 650.

(c) Table with two rows. Row 1 (Time (hr)): 0, 4, 8, 12, 16, 20, 24, 28. Row 2 (Inflow (m3/s)): 10, 20, 30, 30, 25, 20, 35, 12.

What "Calculate" is asking you to do

Apply the standard formula or schedule to data the question has already supplied — a table of readings, cost records, a balance sheet — and produce the number. The method is rarely in doubt; the marks sit in the named intermediate quantities, each of which has to appear as a labelled line.

Structure that answers it

Data as given → formula or standard treatment, named → substitution → each intermediate, labelled → result with units

Where marks are lost

Omitting an intermediate the marking scheme pays for separately, or rounding at an intermediate line so the final figure drifts. In commerce and accountancy, any figure in a statement that no numbered working note supports is treated as unearned.

All UPSC directive words, compared →

How this answer will be evaluated

Approach

(a) calculate: given > formula > substitution > result with units > interpretation | (b) calculate: given > formula > substitution > result with units > interpretation | (c) calculate: given > formula > substitution > result with units > interpretation | (d) explain: definition/context > points in order > small example > short close | (e) calculate: given > formula > substitution > result with units > interpretation Full marks: All parts solved with correct methods, clear steps, and proper units.

Key points expected

  • Convert accumulated rainfall to incremental rainfall
  • Calculate effective rainfall using phi index
  • Scale UH ordinates by effective rainfall depth
  • Add base flow to direct runoff ordinates
  • Calculate area-weighted average precipitation
  • Calculate area-weighted average evaporation
  • Compute runoff coefficient for each sub-area
  • Compute total catchment runoff coefficient

Evaluation rubric

Each sub-part is marked on its own, against the marks and word limit printed on the paper.

  1. (a) Ordinates of the resulting hydrograph for the given storm. 10 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Convert accumulated rainfall to incremental rainfall
    • Calculate effective rainfall using phi index
    • Scale UH ordinates by effective rainfall depth
    • Add base flow to direct runoff ordinates

    Loses marks

    • Using total rainfall instead of effective rainfall
    • Omitting base flow addition

    Earns more

    • Tabular presentation of rainfall and runoff
    • Explicit calculation of effective rainfall depth

    Extra mark

    • Sketch of the resulting hydrograph
  2. (b) Average precipitation, evaporation, and runoff coefficients. 10 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Calculate area-weighted average precipitation
    • Calculate area-weighted average evaporation
    • Compute runoff coefficient for each sub-area
    • Compute total catchment runoff coefficient

    Loses marks

    • Simple arithmetic mean instead of area-weighted
    • Confusing runoff with evaporation

    Earns more

    • Use of Thiesen polygon or area-weighted method
    • Clear tabulation of sub-area data

    Extra mark

    • Sketch of catchment sub-areas
  3. (c) Outflow hydrograph routed through river reach. 10 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Apply Muskingum equation with given x and K
    • Calculate outflow for each time step
    • Use initial outflow as starting condition
    • Present outflow ordinates in a table

    Loses marks

    • Using wrong Muskingum coefficients
    • Skipping intermediate time steps

    Earns more

    • Step-by-step calculation for each time interval
    • Verification of mass balance

    Extra mark

    • Graphical representation of inflow and outflow
  4. (d) Significance of water quality parameters. 10 marks

    explain— definition/context → points in order → small example → short close

    Must cover

    • Define each parameter (Nitrites, Nitrates, E-coli, BOD, DO)
    • Explain health or environmental significance
    • Link parameters to water quality criteria
    • Provide context for each parameter

    Loses marks

    • Defining parameters without explaining significance
    • Confusing nitrites with nitrates

    Earns more

    • Reference to standard water quality limits
    • Explanation of interrelationships between parameters

    Extra mark

    • Table summarizing parameters and their significance
  5. (e) Flow velocity for effective particle removal. 10 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Calculate settling velocity using Stokes' law
    • Determine overflow rate for the settling tank
    • Ensure flow velocity does not exceed settling velocity
    • State assumptions about particle behavior

    Loses marks

    • Using wrong formula for settling velocity
    • Ignoring tank dimensions in calculation

    Earns more

    • Correct application of Stokes' law
    • Clear calculation of tank dimensions and flow rate

    Extra mark

    • Discussion of factors affecting settling efficiency

Model answer coming soon

Every evaluation on this site is marked against a verified model answer. This question's answer is still being written; evaluation opens the moment it lands.

More from Civil Engineering 2023 Paper II