Civil Engineering 2025 Paper II 50 marks Solve

Paper II — Q2

(a) A contractor intends to bid for erecting a statue at a square in an urban area. The various activities of the entire project…

(a)

A contractor intends to bid for erecting a statue at a square in an urban area. The various activities of the entire project are given below :

ActivityActivity NameRemark
AMake statueStarting activity
BLay foundationStarting activity
CConstruct platformFollows B (starts after laying foundation)
DErect statueFinishing activity and follows A and C

The project is expected to take 18 days to complete having a variance of 4 days. Determine in how many days the contractor would expect the project to be completed with a probability of 99%. For probability of 98.93%, the corresponding normal deviate Z value is +2.3 and for probability of 99.18%, Z value is +2.4. Further, if the contractor intends to complete the project in 17 days by crashing the activities, determine how much total project cost would the contractor expect. The normal and crash duration, and associated cost are given in the table below for various activities :

ActivityNormal ActivityCrash Activity
Duration (in days)Cost (in ₹)Duration (in days)Cost (in ₹)
A86,00059,000
B42,00034,000
C85,00075,500
D63,00037,500

For the entire project, the indirect cost is ₹ 500 per day. 20 marks

(b)
(i)

A taxi driver was fined for crossing the traffic signal at right-angled road intersection. He claimed that the signal was faultily designed and the duration of amber light is not sufficient. Using the following data, verify the correctness of the driver's claim :

Road width at intersection = 20 m Speed limit at road = 60 kmph Amber light duration = 4.0 s Comfortable deceleration = 3.0 m/s² Car length = 4.0 m Perception reaction time = 1.2 s 10 marks

(ii)

Explain with sketches how the subsurface drainage system is provided to lower the water table in road. 5 marks

(c)

Calculate the maximum number of wagons of weight 80 tonnes each that can be pulled by a locomotive having hauling capacity of 16 tonnes. The weight of the locomotive is 100 tonnes and the train has to run at a speed of 60 kmph on a straight level BG track. Assume rolling resistance of wagon and locomotive as 1.6 kg/tonne and 2.0 kg/tonne respectively.

Also, calculate the hauling capacity of the locomotive required if the train has to climb a gradient of 1 in 150 in 1° curve. 15 marks

हिंदी में प्रश्न पढ़ें
(a)

एक शहरी क्षेत्र में एक चौराहे पर मूर्ति स्थापित करने के लिए एक ठेकेदार बोली लगाने का इरादा रखता है। पूरी परियोजना की विभिन्न गतिविधियाँ नीचे दी गई हैं :

4 दिनों के प्रसरण के साथ परियोजना के 18 दिनों में पूर्ण होने की अपेक्षा है। निर्धारित कीजिए कि 99% प्रायिकता के साथ परियोजना के पूर्ण होने के लिए ठेकेदार कितने दिनों की अपेक्षा करेगा। 98.93% प्रायिकता के संगत सामान्य विचलन Z का मान +2.3 तथा 99.18% प्रायिकता के संगत Z का मान +2.4 है। इसके अतिरिक्त, यदि ठेकेदार गतिविधियों के क्रैश द्वारा परियोजना को 17 दिनों में पूर्ण करने का इरादा रखता है, तो निर्धारित कीजिए कि ठेकेदार कितनी सकल परियोजना लागत की अपेक्षा करेगा। विभिन्न गतिविधियों के लिए सामान्य तथा क्रैश अवधि और संबद्ध लागत नीचे सारणी में दी गई हैं :

पूरी परियोजना के लिए अप्रत्यक्ष लागत ₹ 500 प्रतिदिन है। (20 अंक)

(b)
(i)

एक टैक्सी चालक पर समकोणीय सड़क चौराहे पर यातायात संकेत पार करने के लिए जुर्माना लगाया गया। उसने दावा किया कि संकेत दोषपूर्ण अभिकल्पित था और पीली (एम्बर) बत्ती की अवधि पर्याप्त नहीं है। निम्नलिखित आंकड़ों का उपयोग करते हुए चालक के दावे की यथार्थता को जाँचिए :

चौराहे पर सड़क की चौड़ाई = 20 m सड़क पर गति सीमा = 60 km प्रति घंटा पीली (एम्बर) बत्ती की अवधि = 4.0 s आरामदायक मंदन = 3.0 m/s² कार की लंबाई = 4.0 m अनुभूति प्रतिक्रिया समय = 1.2 s (10 अंक)

(ii)

रेखाचित्रों के साथ व्याख्या कीजिए कि सड़क पर भौम जलस्तर को कम करने के लिए अधःस्तल जल-निकासी प्रणाली को कैसे प्रदान किया जाता है। (5 अंक)

(c)

16 टन की ढुलाई क्षमता वाले एक रेल-इंजन द्वारा खींचे जा सकने वाले 80 टन वजन (प्रत्येक) वाले वैगनों की अधिकतम संख्या की गणना कीजिए। रेल-इंजन का भार 100 टन है और रेलगाड़ी को एक सीधे समतल बड़ी लाइन रेलपथ पर 60 km प्रति घंटा की गति से चलना है। वैगन और रेल-इंजन के बेलून (रोलिंग) प्रतिरोध को क्रमशः: 1.6 kg प्रति टन तथा 2.0 kg प्रति टन मान लीजिए।

यदि रेलगाड़ी को 150 में 1 की प्रवणता पर 1° वक्र में चढ़ना है, तो रेल-इंजन की आवश्यक ढुलाई क्षमता की भी गणना कीजिए। (15 अंक)

Q2 of the 2025 UPSC Mains Civil Engineering Paper II, as printed
The question as printed in the 2025 Civil Engineering paper

Model answer

Drafted with AI by UPSC Answer Check against this question's marking rubric, to the expected length. UPSC does not publish answers for Mains — this is one way to score well, not an official key. How we build rubrics and answers.

(a)

The network has two paths: A–D and B–C–D. Normal durations: A–D = 8 + 6 = 14 days; B–C–D = 4 + 8 + 6 = 18 days. Hence normal project duration μ = 18 days, critical path B–C–D. Variance = 4 day², so standard deviation σ = √4 = 2 days. For 99% probability, interpolate between 98.93% (Z = 2.3) and 99.18% (Z = 2.4): Z = 2.3 + ((99.00 − 98.93)/(99.18 − 98.93)) × (2.4 − 2.3) Z = 2.3 + (0.07/0.25) × 0.1 = 2.328 ≈ 2.33. Using T = μ + Zσ: T = 18 + 2.33 × 2 = 22.66 days ≈ 22.7 days. So the contractor can expect completion within about 22.66 days with 99% probability.

For crashing to 17 days, cost slopes: A = (9000 − 6000)/(8 − 5) = 1000 ₹/day B = (4000 − 2000)/(4 − 3) = 2000 ₹/day C = (5500 − 5000)/(8 − 7) = 500 ₹/day D = (7500 − 3000)/(6 − 3) = 1500 ₹/day

The critical path is B–C–D. To reduce project duration from 18 to 17 days, crash the critical activity with least slope, i.e. C, by 1 day. New C duration = 7 days. Direct cost = 6000 + 2000 + 5500 + 3000 = 16,500 ₹. Indirect cost for 17 days = 500 × 17 = 8,500 ₹. Total project cost = 16,500 + 8,500 = 25,000 ₹.

(b)(i)

Required amber time for safe signal design is given by A = t_r + v/(2a) + (W + L)/v, where t_r = perception-reaction time, v = speed, a = comfortable deceleration, W = road width, L = car length. Speed v = 60 kmph = 60 × 5/18 = 50/3 m/s = 16.67 m/s. A = 1.2 + (50/3)/(2 × 3) + (20 + 4)/(50/3) A = 1.2 + 25/9 + 36/25 A = 1.2 + 2.7778 + 1.44 = 5.4178 s ≈ 5.42 s. Provided amber duration = 4.0 s. Since 4.0 s < 5.42 s, the amber period is insufficient. If amber and all-red are considered separately, stopping requirement is 1.2 + 2.7778 = 3.98 s and clearing time is 1.44 s, so total change interval still needs 5.42 s. Therefore the driver’s claim is correct.

(b)(ii)

Subsurface drainage is provided to intercept seepage and lower the water table below the road subgrade. A longitudinal perforated pipe or French drain is laid in a trench along one or both shoulders of the road. The trench is filled with graded gravel/sand filter around the pipe, and a geotextile is wrapped around the filter to prevent clogging. Transverse collector drains are provided at intervals to intercept cross-flow and join the longitudinal drain. The collected water is led by outlet pipes to a side drain, natural stream, or sump. Sketch description: In cross-section, the road crust lies above the lowered water table; on the shoulder, a trench contains a perforated pipe at the bottom, surrounded by gravel and geotextile, with an outlet pipe. In plan, longitudinal drains run parallel to the road and are connected by transverse drains at regular spacing. This draws down the water table and keeps the subgrade dry.

Diagram: Subsurface drainage of a road: cross-section with longitudinal trench drains and plan with transverse collectors

(c)

Train resistance on a BG track is taken from the standard empirical expression R = 0.0016W + 0.00008WV + 0.0000006WV² (tonnes, W in tonnes, V in km/h), where the first term is the rolling resistance (given here as 1.6 kg/t for wagons and 2.0 kg/t for the locomotive), the second is the speed-dependent resistance and the third is wind resistance. Since the speed is specified, the speed and wind terms must be included. At V = 60 km/h: speed term = 0.00008 × 60 = 0.0048 t/t (4.8 kg/t); wind term = 0.0000006 × 60² = 0.00216 t/t (2.16 kg/t). Together = 6.96 kg/t.

Level straight track.

  • Locomotive: 100 × (2.0 + 6.96) = 896 kg = 0.896 t
  • Each wagon: 80 × (1.6 + 6.96) = 684.8 kg = 0.6848 t
  • Hauling capacity = total resistance: 16 = 0.896 + 0.6848n, so n = 15.104/0.6848 = 22.06
  • Maximum number of wagons = 22

Gradient 1 in 150 on a 1° curve (same train).

  • Train weight W = 100 + 22 × 80 = 1,860 t
  • Level-track resistance = 0.896 + 22 × 0.6848 = 15.962 t
  • Gradient resistance = W/150 = 1,860/150 = 12.400 t
  • Curve resistance (BG) = 0.0004 W D = 0.0004 × 1,860 × 1 = 0.744 t
  • Required hauling capacity = 15.962 + 12.400 + 0.744 = 29.11 t ≈ 29.1 tonnes

If only the given rolling resistances are used and the speed terms are ignored, the arithmetic gives n = (16,000 − 200)/128 = 123 wagons and a required hauling capacity of about 86.2 t on the gradient. That result ignores the resistance that rises with speed, which is why a 16 t tractive effort appears to haul nearly 10,000 t; the value of 22 wagons is the realistic one.

How this answer will be evaluated

Framework: PERT/CPM, Traffic Engineering, Railway Engineering

What earns full marks: All calculations correct with clear steps, proper units, and complete diagrams where required.

Evaluation rubric

Each sub-part is marked on its own, against the marks and word limit printed on the paper.

  1. (a) Determine project duration for 99% probability and total cost for 17-day completion. 20 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Network paths A–D (14 d) and B–C–D (18 d); critical path B–C–D; σ = 2 days
    • Z for 99% interpolated = 2.328; T = 18 + 2.33 × 2 = 22.66 days
    • Crash cost slopes: A 1000, B 2000, C 500, D 1500 ₹/day; crash C by 1 day (least slope on critical path)
    • Direct 16 500 + indirect (500 × 17 = 8 500) = ₹25 000

    Loses marks

    • Incorrect critical path identification
    • Omits indirect cost in total calculation
    • Wrong Z-value application or formula

    Earns more

    • Correctly identifies non-critical activities for crashing
    • Shows step-by-step cost calculation for each day reduced
    • Verifies final project duration matches 17 days

    Extra mark

    • Draws network diagram with activity durations
    • States assumptions about crashing sequence
  2. (b)(i) Verify if amber light duration is sufficient for safe stopping. 10 marks

    justify— claim → 3-4 reasons → evidence → conclusion

    Must cover

    • Amber A = tr + v/(2a) + (W + L)/v = 1.2 + 2.778 + 1.44 = 5.42 s
    • Provided 4.0 s < 5.42 s → amber insufficient; driver's claim correct
    • Speed conversion 60 kmph = 16.67 m/s; stopping part 3.98 s, clearing part 1.44 s

    Loses marks

    • Incorrect unit conversion
    • Omits perception-reaction distance
    • Wrong braking distance formula

    Earns more

    • Clearly states driver's claim is valid/invalid
    • Shows all unit conversions explicitly
    • Provides numerical comparison with margin

    Extra mark

    • Draws simple diagram of stopping distance components
    • Mentions standard values for perception time
  3. (b)(ii) Explain subsurface drainage system for lowering water table. 5 marks

    describe— define → structure or process in order → labelled diagram → significance

    Must cover

    • Subsurface drainage intercepts seepage and lowers the water table below the subgrade
    • Trench with perforated pipe surrounded by graded filter and geotextile (anti-clogging)
    • Transverse collectors join the longitudinal drains; outlets lead water to side drains
    • Sketches (cross-section and plan) provided in the answer

    Loses marks

    • Confuses with surface drainage
    • No sketch or diagram provided
    • Vague description without components

    Earns more

    • Includes labelled sketch of drainage system
    • Mentions materials used (gravel, geotextile)
    • Explains maintenance requirements

    Extra mark

    • References IS code for drainage design
    • Mentions specific applications (high water table areas)
  4. (c) Calculate max wagons on level track and required capacity on gradient. 15 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Train resistance R = 0.0016W + 0.00008WV + 0.0000006WV² (BG): speed + wind terms at 60 km/h = 6.96 kg/t added to given rolling resistances
    • Loco 0.896 t, each wagon 0.6848 t; n = (16 − 0.896)/0.6848 = 22.06 → 22 wagons (123 if speed terms are wrongly ignored)
    • On gradient: W = 1860 t; gradient W/150 = 12.4 t; curve 0.0004WD = 0.744 t; level resistance 15.962 t
    • Required hauling capacity = 15.962 + 12.4 + 0.744 ≈ 29.1 t

    Loses marks

    • Ignoring speed/wind resistance although speed is specified
    • Omits curve resistance in gradient case
    • Wrong formula for gradient resistance

    Earns more

    • Shows all resistance components separately
    • Uses correct formulas for gradient and curve resistance
    • Provides final answer with units (number of wagons)

    Extra mark

    • States assumptions about train composition
    • Mentions safety factor in calculation
What "Solve" is asking you to do

Choose the method, then carry it through to a final answer. Identifying what kind of problem this is and why that method applies is the first thing marked; a correct figure arrived at invisibly earns almost nothing.

Structure that answers it

Given data and what is required → method chosen, with the reason it applies → set-up (equation, circuit, free body, trial balance) → working, step by step → answer with units and any condition of validity

Where marks are lost

Doing the middle steps mentally and writing only the result. In mathematics papers, a further loss comes from giving a decimal where the exact value in surds or fractions was wanted, or from skipping the justification a part explicitly asks for.

All UPSC directive words, compared →

Practice this exact question

Write your answer and it is marked point by point against the model answer above — what you covered, what you missed, what you got wrong.

Evaluate my answer →

More from Civil Engineering 2025 Paper II

Write this answer and get it marked in about 20 seconds

Free account: 5 AI evaluations a month, marked against the rubric above.

Start free

Already have an account? Log in