Civil Engineering 2025 Paper II 50 marks Solve

Q2

(a) A contractor intends to bid for erecting a statue at a square in an urban area. The various activities of the entire project are given below : | Activity | Activity Name | Remark | |----------|---------------|--------| | A | Make statue | Starting activity | | B | Lay foundation | Starting activity | | C | Construct platform | Follows B (starts after laying foundation) | | D | Erect statue | Finishing activity and follows A and C | The project is expected to take 18 days to complete having a variance of 4 days. Determine in how many days the contractor would expect the project to be completed with a probability of 99%. For probability of 98.93%, the corresponding normal deviate Z value is +2.3 and for probability of 99.18%, Z value is +2.4. Further, if the contractor intends to complete the project in 17 days by crashing the activities, determine how much total project cost would the contractor expect. The normal and crash duration, and associated cost are given in the table below for various activities : | Activity | Normal Activity | | Crash Activity | | |----------|-----------------|---|----------------|---| | | Duration (in days) | Cost (in ₹) | Duration (in days) | Cost (in ₹) | | A | 8 | 6,000 | 5 | 9,000 | | B | 4 | 2,000 | 3 | 4,000 | | C | 8 | 5,000 | 7 | 5,500 | | D | 6 | 3,000 | 3 | 7,500 | For the entire project, the indirect cost is ₹ 500 per day. (20 marks) (b) (i) A taxi driver was fined for crossing the traffic signal at right-angled road intersection. He claimed that the signal was faultily designed and the duration of amber light is not sufficient. Using the following data, verify the correctness of the driver's claim : Road width at intersection = 20 m Speed limit at road = 60 kmph Amber light duration = 4.0 s Comfortable deceleration = 3.0 m/s² Car length = 4.0 m Perception reaction time = 1.2 s (10 marks) (ii) Explain with sketches how the subsurface drainage system is provided to lower the water table in road. (5 marks) (c) Calculate the maximum number of wagons of weight 80 tonnes each that can be pulled by a locomotive having hauling capacity of 16 tonnes. The weight of the locomotive is 100 tonnes and the train has to run at a speed of 60 kmph on a straight level BG track. Assume rolling resistance of wagon and locomotive as 1.6 kg/tonne and 2.0 kg/tonne respectively. Also, calculate the hauling capacity of the locomotive required if the train has to climb a gradient of 1 in 150 in 1° curve. (15 marks)

हिंदी में प्रश्न पढ़ें

(a) एक शहरी क्षेत्र में एक चौराहे पर मूर्ति स्थापित करने के लिए एक ठेकेदार बोली लगाने का इरादा रखता है। पूरी परियोजना की विभिन्न गतिविधियाँ नीचे दी गई हैं : 4 दिनों के प्रसरण के साथ परियोजना के 18 दिनों में पूर्ण होने की अपेक्षा है। निर्धारित कीजिए कि 99% प्रायिकता के साथ परियोजना के पूर्ण होने के लिए ठेकेदार कितने दिनों की अपेक्षा करेगा। 98.93% प्रायिकता के संगत सामान्य विचलन Z का मान +2.3 तथा 99.18% प्रायिकता के संगत Z का मान +2.4 है। इसके अतिरिक्त, यदि ठेकेदार गतिविधियों के क्रैश द्वारा परियोजना को 17 दिनों में पूर्ण करने का इरादा रखता है, तो निर्धारित कीजिए कि ठेकेदार कितनी सकल परियोजना लागत की अपेक्षा करेगा। विभिन्न गतिविधियों के लिए सामान्य तथा क्रैश अवधि और संबद्ध लागत नीचे सारणी में दी गई हैं : पूरी परियोजना के लिए अप्रत्यक्ष लागत ₹ 500 प्रतिदिन है। (20 अंक) (b) (i) एक टैक्सी चालक पर समकोणीय सड़क चौराहे पर यातायात संकेत पार करने के लिए जुर्माना लगाया गया। उसने दावा किया कि संकेत दोषपूर्ण अभिकल्पित था और पीली (एम्बर) बत्ती की अवधि पर्याप्त नहीं है। निम्नलिखित आंकड़ों का उपयोग करते हुए चालक के दावे की यथार्थता को जाँचिए : चौराहे पर सड़क की चौड़ाई = 20 m सड़क पर गति सीमा = 60 km प्रति घंटा पीली (एम्बर) बत्ती की अवधि = 4.0 s आरामदायक मंदन = 3.0 m/s² कार की लंबाई = 4.0 m अनुभूति प्रतिक्रिया समय = 1.2 s (10 अंक) (ii) रेखाचित्रों के साथ व्याख्या कीजिए कि सड़क पर भौम जलस्तर को कम करने के लिए अधःस्तल जल-निकासी प्रणाली को कैसे प्रदान किया जाता है। (5 अंक) (c) 16 टन की ढुलाई क्षमता वाले एक रेल-इंजन द्वारा खींचे जा सकने वाले 80 टन वजन (प्रत्येक) वाले वैगनों की अधिकतम संख्या की गणना कीजिए। रेल-इंजन का भार 100 टन है और रेलगाड़ी को एक सीधे समतल बड़ी लाइन रेलपथ पर 60 km प्रति घंटा की गति से चलना है। वैगन और रेल-इंजन के बेलून (रोलिंग) प्रतिरोध को क्रमशः: 1.6 kg प्रति टन तथा 2.0 kg प्रति टन मान लीजिए। यदि रेलगाड़ी को 150 में 1 की प्रवणता पर 1° वक्र में चढ़ना है, तो रेल-इंजन की आवश्यक ढुलाई क्षमता की भी गणना कीजिए। (15 अंक)

Directive word: Solve

This question asks you to solve. The directive word signals the depth of analysis expected, the structure of your answer, and the weight of evidence you must bring.

See our UPSC directive words guide for a full breakdown of how to respond to each command word.

How this answer will be evaluated

Approach

Begin by identifying the critical path and calculating expected project duration with probability for part (a), then verify amber light timing using kinematic equations for part (b)(i), sketch subsurface drainage for (b)(ii), and finally compute hauling capacity and gradient resistance for part (c). Allocate approximately 40% time to part (a) due to its 20 marks and complexity involving PERT and crashing, 30% to part (b) combined, and 30% to part (c). Present all calculations systematically with clear labeling of each sub-part.

Key points expected

  • Part (a): Identify critical path (B-C-D), calculate expected duration (18 days), determine Z-value for 99% probability (interpolate to Z=2.37), compute completion time (~22.7 days), perform crashing analysis by cost slope to reduce duration to 17 days at minimum additional cost including indirect costs
  • Part (b)(i): Calculate stopping sight distance using perception-reaction time and braking distance, determine safe amber time using dilemma zone concept (ISD = v*t + v²/2a + vehicle length), compare with given 4.0s amber duration to verify driver's claim
  • Part (b)(ii): Sketch longitudinal section showing perforated pipe, filter media, outlet structure, and lowered water table position with proper labeling for subsurface drainage in road construction
  • Part (c): Calculate total train resistance on level track (rolling resistance of locomotive + wagons), equate to hauling capacity to find maximum wagons (16), then compute required hauling capacity for 1 in 150 gradient with 1° curve using Ruling Gradient formula including curve resistance (0.04% per degree)

Evaluation rubric

DimensionWeightMax marksExcellentAveragePoor
Concept correctness20%10Correctly identifies critical path B-C-D for (a), applies PERT probability formula with proper Z-interpolation, uses correct dilemma zone/amber time formula for (b)(i), and applies Indian Railways standard formulas for gradient and curve resistance in (c) including 0.04% per degree curve resistanceIdentifies correct critical path but makes minor errors in probability calculation or crashing logic; applies basic kinematic equations for amber time but misses dilemma zone nuance; computes basic hauling capacity but omits curve resistance or uses incorrect gradient formulaWrong critical path identification (A-D or others), incorrect application of normal distribution for probability, uses simple speed-distance-time for amber verification without deceleration, or confuses hauling capacity with tractive effort without resistance calculations
Numerical accuracy20%10Precise calculations: Z=2.37 for 99% probability yielding ~22.7 days, minimum crashing cost with correct cost slopes (A:1000/day, B:2000/day, C:500/day, D:1500/day) selecting C and A, total cost ₹23,500; amber time calculation showing 4.0s is insufficient; 16 wagons on level, ~23 tonnes hauling capacity for gradientCorrect methodology but minor arithmetic errors in interpolation, crashing cost summation, or unit conversions (kmph to m/s); reasonable wagon count with slight resistance calculation errors; gradient calculation missing one componentMajor calculation errors: wrong Z-value application, incorrect cost slope calculations leading to wrong crashing decisions, unit conversion errors (kmph to m/s), or order-of-magnitude errors in hauling capacity due to resistance formula mistakes
Diagram quality15%7.5Clear AOA or AON network diagram for (a) showing all activities with durations and dependencies; neat labeled sketch for (b)(ii) showing pipe, gravel envelope, impervious layer, original and lowered water table, and outlet; well-organized tabular presentation for crashing analysisBasic network diagram without clear node numbering or missing some dependencies; simple drainage sketch missing some labels or layers; tables present but not optimally formattedMissing network diagram, confusing hand-drawn sketches without labels, or no diagram for (b)(ii) despite explicit requirement; illegible or poorly organized presentation that hinders evaluation
Step-by-step derivation25%12.5Systematic presentation: for (a) shows ES/EF/LS/LF calculations, variance along critical path, Z-formula Te = T + Zσ with interpolation shown, cost slope table, crashing steps with iteration; for (b)(i) derives ISD formula with substitution; for (c) shows resistance balance equation and gradient resistance derivationShows key steps but skips some intermediate calculations like ES/EF table or assumes Z-value without interpolation; presents final formulas with values substituted but limited derivation shown; basic equation setup for hauling capacityJumps to final answers without showing workings, missing critical steps like critical path identification method, no formula statement before substitution, or disorganized calculation sequence that prevents verification
Practical interpretation20%10Interprets 99% probability completion time as conservative bid estimate with 1% risk; explains crashing decision considers both direct and indirect costs (₹500/day); concludes amber time is insufficient based on calculated safe time (>4s), validating driver's claim; relates hauling capacity to Indian Railways BG standards and operational safety marginsStates final answers without contextual interpretation; basic conclusion on crashing being cost-effective or not; simple valid/invalid statement for driver's claim without engineering justification; standard answer for railway capacity without operational contextNo interpretation of results, fails to conclude whether project should be bid or crashed, no verdict on driver's claim validity despite calculation, or ignores practical implications of gradient hauling capacity for train operations

Practice this exact question

Write your answer, then get a detailed evaluation from our AI trained on UPSC's answer-writing standards. Free first evaluation — no signup needed to start.

Evaluate my answer →

More from Civil Engineering 2025 Paper II