Electrical Engineering 2025 Paper II 50 marks Compulsory Evaluate

Paper II — Q1

(a) The block diagram of a system is as shown below : Evaluate the overall transfer function (Y(s))/(R(s)) using block diagram…

(a)

The block diagram of a system is as shown below : Evaluate the overall transfer function (Y(s))/(R(s)) using block diagram reduction technique. 10 marks

(b)
(i)

Explain the operation performed by 8085 microprocessor when the following instructions are executed : JMP unconditionally

(ii)

POP

(iii)

PUSH

(iv)

RET

(v)

STC 2×5=10

(c)

For the circuit shown in the figure below give expression for the overall uncertainty in the value of combined resistance R. Further, evaluate the overall uncertainty in the value of combined resistance R, when individual values of the resistors are as R₁ = 50 ± 0·1 Ω, R₂ = 100 ± 0·2 Ω, R₃ = 100 ± 0·2 Ω. 10 marks

(d)
(i)

A factory has a fixed load of 860 kW and is operating at 0·85 power factor. The electric utility company offers to supply energy at the following two alternate rates : LV supply at ₹ 30/kVA max demand/annum + 12 paise/kWh

(ii)

HV supply at ₹ 25/kVA max demand/annum + 10 paise/kWh The HV switchgear costs ₹ 50/kVA and switchgear losses at full load amount to 4%. Interest and depreciation charges for switchgear are 10% of the capital cost. If the factory is to work 48 hours/week, then determine the more economical tariff option. 10 marks

(e)

If the generator polynomial is (x⁴ + x + 1) and the message bits are 1101101, then obtain the CRC code. 10 marks

हिंदी में प्रश्न पढ़ें
(a)

एक तंत्र का खंड आरेख नीचे दर्शाया गया है : खंड आरेख लघुकरण विधि का उपयोग करते हुए समग्र अंतरण फलन (Y(s))/(R(s)) का मान निकालिये। 10

(b)
(i)

8085 सूक्ष्म-संसाधित्र (माइक्रोप्रोसर) द्वारा की जाने वाली क्रियाविधि की व्याख्या कीजिए, जब निम्नलिखित निर्देशों का निष्पादन होता है : JMP अप्रतिबंधित (अनकंडीशनली)

(ii)

POP

(iii)

PUSH

(iv)

RET

(v)

STC 2×5=10

(c)

नीचे चित्र में दर्शाये गये परिपथ के लिए इसके संयुक्त प्रतिरोध R के मान में समग्र अनिश्चितता के लिये व्यंजक दीजिये। इसके आगे, संयुक्त प्रतिरोध R के मान में समग्र अनिश्चितता का मान निकालिये, जब अन्य प्रतिरोधों के वैयक्तिक मान हैं R₁ = 50 ± 0·1 Ω, R₂ = 100 ± 0·2 Ω, R₃ = 100 ± 0·2 Ω। 10

(d)
(i)

एक कारखाने का नियत भार 860 kW है और यह 0·85 के शक्ति गुणक पर कार्य करता है। विद्युत उपयोगिता कम्पनी इसे ऊर्जा प्रदान करने के लिये निम्नलिखित दो वैकल्पिक दरें प्रस्तावित करती है : LV आपूर्ति ₹ 30/kVA अधिकतम माँग/वर्ष + 12 पैसे/kWh पर

(ii)

HV आपूर्ति ₹ 25/kVA अधिकतम माँग/वर्ष + 10 पैसे/kWh पर HV स्विचगियर की कीमत ₹ 50/kVA और पूर्ण भार पर इसकी हानि 4% है। स्विचगियर का ब्याज और मूल्यह्रास शुल्क इसकी पूँजी लागत का 10% है। यदि कारखाना एक हफ्ते में 48 घंटे चलता है, तो अधिक किफायती ऊर्जा की वैकल्पिक दर का निर्धारण कीजिये। 10

(e)

यदि जनित्र (जनरेटर) बहुपद (x⁴ + x + 1) है और संदेश बिट 1101101 है, तो CRC कूट (कोड) प्राप्त कीजिये। 10

Q1 of the 2025 UPSC Mains Electrical Engineering Paper II, as printed
The question as printed in the 2025 Electrical Engineering paper

The figure this question refers to, in words

The question paper is a scan and the diagram did not survive as text. This is the figure as read from the original page — every component, value and label — so the question can be worked from the text below.

(a) A block diagram of a control system. The input is R(s) and the output is Y(s). The signal R(s) enters a summing junction (J1) with a positive sign. The output of J1 enters a block G1. The output of G1 enters a second summing junction (J2) with a positive sign. The output of J2 enters a block G2. The output of G2 enters a third summing junction (J3) with a positive sign. The output of J3 is Y(s). There are three feedback/feedforward paths: 1. A path from the output of J2 goes through a block H1 and enters J2 with a negative sign. 2. A path from the output of J2 goes through a block H2 and enters J1 with a negative sign. 3. A path from the input R(s) goes through a block G3 and enters J3 with a positive sign.

(c) A circuit diagram showing a combination of three resistors. The input terminals are on the left. The top terminal connects to a resistor labeled R1. The right side of R1 connects to a node where the circuit splits into two parallel branches. The top branch contains a resistor labeled R2. The bottom branch contains a resistor labeled R3. The right sides of R2 and R3 connect together at a node, which then connects to the bottom input terminal. The total equivalent resistance of the network is labeled R with an arrow pointing into the terminals.

Model answer

Drafted with AI by UPSC Answer Check against this question's marking rubric, to the expected length. UPSC does not publish answers for Mains — this is one way to score well, not an official key. How we build rubrics and answers.

(a) Block diagram reduction

Label the summing-junction outputs E1 (at the first junction) and V2 (at the second junction). Reading the figure: H1 is taken from the output Y(s) (after the third summing junction) and returned to the second junction with a negative sign, so it forms a feedback loop around G2; H2 is taken from V2 and returned to the first junction with a negative sign, so it forms a loop around G1; G3 is a feedforward path from R(s) to the output junction.

Node equations: E1 = R − H2V2, V2 = G1E1 − H1Y, Y = G2V2 + G3R.

Step 1 (H2 loop around G1): E1 = R − H2V2 gives V2 = G1(R − H2V2) − H1Y, i.e. V2(1 + G1H2) = G1R − H1Y.

Step 2 (H1 loop around G2): substituting in Y = G2V2 + G3R gives Y(1 + G1H2) = G1G2R − G2H1Y + G3R(1 + G1H2), so Y(1 + G1H2 + G2H1) = R(G1G2 + G3 + G1G3H2).

Hence Y/R = [G1G2 + G3(1 + G1H2)]/(1 + G1H2 + G2H1) = (G1G2 + G3 + G1G3H2)/(1 + G1H2 + G2H1).

Mason's gain formula confirms this: forward paths G1G2 and G3; loops L1 = −G1H2 and L2 = −G2H1 touch each other, so Δ = 1 + G1H2 + G2H1, while the G3 path is non-touching with the H2 loop (Δ2 = 1 + G1H2). Limiting checks: H1 = 0 gives G1G2/(1 + G1H2) + G3, and H2 = 0 gives (G1G2 + G3)/(1 + G2H1).

(b) 8085 instructions

JMP is an unconditional 16-bit jump. It requires 10 T-states: one opcode-fetch cycle, followed by two memory-read cycles that fetch the low and high address bytes, after which PC is loaded with the 16-bit address. No flags are affected. PUSH is a 12 T-state stack instruction. After opcode fetch, it performs two memory-write cycles: SP is decremented and the high-order byte of the register pair is written, then SP is decremented again and the low-order byte is written; for PUSH PSW the accumulator and flag byte are stored. POP is the reverse operation and also takes 10 T-states. It performs two memory-read cycles: the byte at SP is loaded into the low-order register, SP is incremented, the next byte is loaded into the high-order register, and SP is incremented again; POP PSW restores the accumulator and flags. RET is an unconditional return instruction, not a conditional one, and takes 10 T-states. It pops the 16-bit return address from the stack into PC using two memory reads and two SP increments; flags are unchanged. STC is a 4 T-state flag instruction. It sets the carry flag to 1, leaves the other flags unchanged, and involves no memory read or write.

(c) Uncertainty in combined resistance

The circuit is R1 in series with the parallel combination of R2 and R3, so R=R1+R2R3/(R2+R3). Because R is nonlinear in R2 and R3, the partial-derivative method is used. For independent uncertainties, the absolute uncertainty is ΔR=[(∂R/∂R1 ΔR1)²+(∂R/∂R2 ΔR2)²+(∂R/∂R3 ΔR3)²]¹/2. Here ∂R/∂R1=1, ∂R/∂R2=R3²/(R2+R3)², and ∂R/∂R3=R2²/(R2+R3)². Hence ΔR=[(ΔR1)²+(R3²/(R2+R3)² ΔR2)²+(R2²/(R2+R3)² ΔR3)²]¹/2. Substituting R1=50 Ω, R2=R3=100 Ω, ΔR1=0.1 Ω, ΔR2=ΔR3=0.2 Ω gives R=50+100×100/(100+100)=100 Ω. The derivative terms are 1, 0.25 and 0.25, so ΔR=[0.1²+(0.25×0.2)²+(0.25×0.2)²]¹/2=[0.01+0.0025+0.0025]¹/2=0.122 Ω. To the precision justified by the data, R=100±0.12 Ω by root-sum-square. If the tolerances are interpreted as worst-case limits, the bound is 0.1+0.05+0.05=0.20 Ω.

(d) Tariff economics

The maximum demand of the factory is 860/0.85=1011.76 kVA. The annual running hours are 48×52=2496 h, so the annual load energy is 860×2496=2,146,560 kWh. The LV tariff gives an annual demand charge of 30×1011.76=₹30,353 and an energy charge of 12 paise/kWh, i.e. ₹0.12×2,146,560=₹257,587. Total LV cost is therefore ₹287,940 per annum. For HV supply, the switchgear losses are 4% of full load. In apparent power this is 0.04×1011.76=40.47 kVA, and in active power at the same power factor it is 0.04×860=34.4 kW. These losses must be included both in the billed maximum demand and in the energy billed. The billed maximum demand is 1011.76+40.47=1052.24 kVA, so the HV demand charge is 25×1052.24=₹26,306. The billed energy is 2,146,560+34.4×2496=2,232,422 kWh, giving an energy charge of ₹0.10×2,232,422=₹223,242. The switchgear capital cost is 50×1011.76=₹50,588, and 10% interest and depreciation gives an annual charge of ₹5,059. Total HV cost is 26,306+223,242+5,059=₹254,607 per annum. If the switchgear capital is assessed on the billed kVA rather than the load kVA, the annual charge rises only to ₹5,261 and the total to ₹254,809, so the verdict is unchanged. HV supply is therefore more economical by about ₹33,333 per annum.

(e) CRC code

The generator polynomial x⁴+x+1 corresponds to the 5-bit divisor 10011. Since the generator degree is 4, four zeros are appended to the 7-bit message 1101101, giving 11011010000. Binary division is performed by XOR. The first five bits 11011⊕10011=01000; bringing down the next 0 gives 10000. Then 10000⊕10011=00011; bringing down 1 gives 00111. The leading bit is 0, so bring down 0 to get 01110; again the leading bit is 0, so bring down 0 to get 11100. Now 11100⊕10011=01111; bringing down 0 gives 11110. Then 11110⊕10011=01101; bringing down 0 gives 11010. Finally 11010⊕10011=01001. The 4-bit remainder is 1001. The CRC code is the message followed by this remainder: 11011011001. As a check, dividing 11011011001 by 10011 gives remainder 0000, confirming that the codeword is divisible by the generator polynomial.

How this answer will be evaluated

What earns full marks: Methodical steps, correct formulas, accurate calculations, clear presentation.

Evaluation rubric

Each sub-part is marked on its own, against the marks and word limit printed on the paper.

  1. (a) Overall transfer function Y(s)/R(s) via block diagram reduction. 10 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Figure read correctly: H1 = feedback from Y(s) to J2(−) (loop around G2); H2 = feedback from V2 to J1(−) (loop around G1); G3 = feedforward R→output junction
    • Node equations: E1 = R − H2V2; V2 = G1E1 − H1Y; Y = G2V2 + G3R
    • Algebra: V2(1+G1H2) = G1R − H1Y then Y(1+G1H2+G2H1) = R(G1G2+G3+G1G3H2)
    • Result Y/R = [G1G2 + G3(1+G1H2)]/(1+G1H2+G2H1); Mason/limiting-case check

    Loses marks

    • Sign errors in feedback loops
    • Skipping reduction steps

    Earns more

    • Correct handling of cross-coupling
    • Verification via Mason's gain formula

    Extra mark

    • Mention of stability implications
  2. (b) Operation of 8085 instructions: JMP, POP, PUSH, RET, STC. 10 marks

    explain— definition/context → points in order → small example → short close

    Must cover

    • JMP: unconditional 16-bit jump, 10 T-states (opcode fetch + 2 memory reads), PC ← 16-bit address, no flags affected
    • PUSH: 12 T-states, two memory writes, SP decremented twice, high byte then low byte
    • POP: 10 T-states, two memory reads, low then high byte, SP incremented twice (POP PSW restores flags)
    • RET: unconditional, 10 T-states, return address popped into PC; STC: 4 T-states, CY set to 1

    Loses marks

    • Confusing PUSH and POP order
    • Omitting flag effects

    Earns more

    • Mention of cycle counts
    • Effect on specific flags

    Extra mark

    • Example of stack memory layout
  3. (c) Expression and value for uncertainty in combined resistance R. 10 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • R = R1 + R2R3/(R2+R3); partials ∂R/∂R1 = 1, ∂R/∂R2 = R3²/(R2+R3)², ∂R/∂R3 = R2²/(R2+R3)²
    • RSS: ΔR = √[(ΔR1)² + (∂R/∂R2 ΔR2)² + (∂R/∂R3 ΔR3)²]
    • R = 100 Ω; ΔR = √0.015 ≈ 0.122 Ω ≈ 0.12 Ω
    • Worst-case bound 0.20 Ω stated separately

    Loses marks

    • Treating parallel as series
    • Arithmetic errors in substitution

    Earns more

    • Partial differentiation steps shown
    • Correct handling of parallel term

    Extra mark

    • Percentage uncertainty calculation
  4. (d) Comparison of LV vs HV tariff costs to find economical option. 10 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Max demand 1011.76 kVA; 2496 h/yr; annual energy 21,46,560 kWh
    • LV: 30×1011.76 = ₹30,353 + 0.12×21,46,560 = ₹2,57,587 → ₹2,87,940
    • HV: 4% switchgear losses (40.47 kVA / 34.4 kW) billed in demand and energy; demand charge ₹26,306; energy charge ₹2,23,242; capital 50×1011.76 = ₹50,588 with 10% → ₹5,059
    • HV total ₹2,54,607; HV cheaper by ≈₹33,333 → HV is the more economical tariff

    Loses marks

    • Ignoring power factor in kVA calc
    • Missing switchgear interest/depreciation

    Earns more

    • Correct handling of switchgear losses
    • Clear tabulation of costs

    Extra mark

    • Break-even analysis
  5. (e) CRC code for message 1101101 with generator x⁴+x+1. 10 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Generator 10011; append 4 zeros → 11011010000
    • XOR division yields remainder 1001
    • CRC codeword 11011011001; check division by 10011 gives remainder 0

    Loses marks

    • Wrong binary representation of polynomial
    • Arithmetic errors in XOR division

    Earns more

    • Step-by-step division shown
    • Correct identification of remainder

    Extra mark

    • Verification of code divisibility
What "Evaluate" is asking you to do

Judge how well something has performed against the standard it set for itself — its stated aim, mandate or promise — and commit to a verdict. Name the yardstick before you judge; an unanchored judgement reads as opinion.

Structure that answers it

Name the yardstick — stated aim, mandate or benchmark → performance against it → shortfall against it → why the gap exists → verdict

Where marks are lost

Presenting both sides and then declining to decide, or delivering a verdict against a standard you never stated, which makes it look arbitrary.

All UPSC directive words, compared →

Practice this exact question

Write your answer and it is marked point by point against the model answer above — what you covered, what you missed, what you got wrong.

Evaluate my answer →

More from Electrical Engineering 2025 Paper II

Write this answer and get it marked in about 20 seconds

Free account: 5 AI evaluations a month, marked against the rubric above.

Start free

Already have an account? Log in