Civil Engineering 2021 Paper II 50 marks Solve

Paper II — Q6

(a) Two settling tanks – one rectangular, with length to width ratio of 3 : 1 and side water depth of 3·5 m; and the other…

(a)

Two settling tanks – one rectangular, with length to width ratio of 3 : 1 and side water depth of 3·5 m; and the other circular, with side water depth of 4·0 m – are to be designed to treat 20,000 m³/d of water required for a city's water supply. The surface overflow rate for satisfactory removal of solids is 20 m/d. Determine the dimensions of the settling zone of the two tanks. Check for retention time, horizontal velocity and weir overflow rate which should respectively be 3–5 hours, less than 10 m/h and 6 to 10 m³/h per m. Also determine the overall dimensions of the basins keeping length of inlet zone and outlet zone equal to the side water depth of the basin. 20 marks

(b)

Although it would be expected that the value of the ultimate carbonaceous BOD would be as high as the COD, this is seldom the case. What are the reasons for the observed differences? 15 marks

(c)

Determine the storage capacity of a reservoir for the given cropping pattern, canal losses are 15% and reservoir losses are 10%. 15 marks

हिंदी में प्रश्न पढ़ें
(a)

एक शहर के जलप्रदाय के लिए आवश्यक 20,000 m³/d जल के शोधन के लिए दो नि:सादन टंकी, एक आयताकार, लंबाई एवं चौड़ाई का अनुपात 3 : 1 एवं पार्श्व जल गहराई 3·5 m के साथ, एवं दूसरी वृत्ताकार, 4·0 m की पार्श्व जल गहराई के साथ अभिकल्पित की जानी हैं । ठोस कणों को संतोषजनक रूप से पृथक करने के लिए सतह उत्प्लाव दर (सरफेस ओवरफ्लो रेट) 20 m प्रतिदिन है । दोनों टंकियों के नि:सादन क्षेत्र की लंबाई, चौड़ाई ज्ञात कीजिए । धारण समय, क्षैतिज गति, एवं विवर उत्प्लाव दर की जाँच कीजिए, जो कि क्रमशः 3 से 5 घंटे, 10 m प्रति घंटे से कम एवं 6 से 10 m³ प्रति घंटे प्रति m होना चाहिए । साथ ही आगम क्षेत्र एवं निर्गम क्षेत्र की लंबाई को पार्श्व जल गहराई के बराबर रखते हुए बेसिनों की समग्र विमाएँ निर्धारित कीजिए । (20 अंक)

(b)

हालांकि ऐसा अनुमानित है कि चरम कार्बनिक जैविक ऑक्सीजन मांग (बी.ओ.डी.) की मात्रा रासायनिक ऑक्सीजन मांग (सी.ओ.डी.) की मात्रा के समान ही होगी, पर ऐसा शायद ही कभी होता है । इन प्रेक्षित अंतरों के क्या कारण हैं ? (15 अंक)

(c)

प्रदत्त फसल प्रतिरूप (पैटर्न) के लिए एक जलाशय की संग्रहण क्षमता निर्धारित कीजिए । नहर हानि 15% एवं जलाशय हानि 10% है । (15 अंक)

Q6 of the 2021 UPSC Mains Civil Engineering Paper II, as printed
The question as printed in the 2021 Civil Engineering paper

The figure this question refers to, in words

The question paper is a scan and the diagram did not survive as text. This is the figure as read from the original page — every component, value and label — so the question can be worked from the text below.

(c) Table with 5 rows of data and 5 columns. The columns are: Sl. No., Crop, Base period (days), Duty at field (hect./cumec), Area under crop (hect.).

Row 1: 1, Sugarcane, 360, 800, 6500 Row 2: 2, Cotton, 200, 1400, 4200 Row 3: 3, Wheat, 120, 1800, 3100 Row 4: 4, Rice, 120, 900, 3200 Row 5: 5, Vegetables, 120, 700, 1100

Model answer

Drafted with AI by UPSC Answer Check against this question's marking rubric, to the expected length. UPSC does not publish answers for Mains — this is one way to score well, not an official key. How we build rubrics and answers.

(a) Rectangular and circular settling tanks for 20,000 m³/d

Q = 20,000 m³/d = 833.3 m³/h. Settling area for an overflow rate of 20 m³/m²/d: A = Q/SOR = 20,000/20 = 1,000 m².

Rectangular tank (3:1, side water depth 3.5 m): 3W² = 1,000 gives W = 18.3 m and L = 54.8 m for one unit.

  • Retention time = 1,000 × 3.5/20,000 = 0.175 d = 4.2 h, within 3 to 5 h.
  • Horizontal velocity = 833.3/(18.26 × 3.5) = 13.0 m/h, which exceeds 10 m/h. So the flow is split into two parallel units of 500 m² each: W = 12.9 m, L = 38.7 m, depth 3.5 m. Velocity = 416.7/(12.9 × 3.5) = 9.2 m/h, which is acceptable, and retention stays 4.2 h.
  • Weir overflow rate: an end weir only 12.9 m wide gives 416.7/12.9 = 32 m³/h/m, too high. For about 8 m³/h/m, a total weir length of 833.3/8 ≈ 104 m (about 52 m per unit) is provided as finger launders, within the 6 to 10 range.
  • Overall size of each unit = 38.7 + 3.5 (inlet zone) + 3.5 (outlet zone) = 45.7 m × 12.9 m.

Circular tank (side water depth 4.0 m): πD²/4 = 1,000 gives D = 35.7 m.

  • Retention time = 1,000 × 4/20,000 = 0.2 d = 4.8 h, acceptable.
  • Radial velocity at the periphery = 833.3/(π × 35.7 × 4) = 1.9 m/h, which is below 10 m/h.
  • Peripheral weir length = π × 35.7 = 112 m, so the rate = 833.3/112 = 7.4 m³/h/m, within 6 to 10.
  • Taking a 4 m outlet zone all round, with the inlet as a central feed well, the overall diameter is about 35.7 + 2 × 4 = 43.7 m.
Diagram: Rectangular and circular settling tanks: plan and section

(b) Why ultimate carbonaceous BOD is usually less than COD

COD uses a strong chemical oxidant (dichromate) that oxidises almost all organic matter, whereas BOD measures only what bacteria actually consume in respiration. Ultimate carbonaceous BOD would equal COD only if every oxidisable substance were biodegradable and fully oxidised by the seed, which rarely happens. The main reasons are:

  • Biologically resistant organics such as lignin, cellulose in some forms, humic substances, tannins and many synthetic organics are oxidised by dichromate but not by bacteria.
  • Part of the biodegradable carbon is built into new cells and not oxidised to CO₂ and water, so the oxygen consumed is less than the full chemical demand.
  • Some organics degrade so slowly that they are not fully oxidised in the test period, which understates the ultimate demand.
  • Toxic substances such as heavy metals, cyanide, extreme pH or residual chlorine inhibit the seed organisms, so the BOD result is low.
  • COD also counts oxidisable inorganic species such as Fe²⁺, S²⁻, SO₃²⁻ and NO₂⁻, which do not exert carbonaceous BOD.
  • BOD needs an acclimatised seed, correct nutrients and dilution, so poor seeding or errors in the test further lower the result.

The BOD/COD ratio is therefore below 1: roughly 0.4 to 0.8 for domestic sewage, and lower for industrial effluents with a large non-biodegradable fraction.

(c) Reservoir storage for the given cropping pattern

For each crop, discharge = A/D and volume = (A/D) × B, in cumec-days (D in ha/cumec, B in days).

  • Sugarcane: 6500/800 = 8.125 cumec × 360 = 2,925.0
  • Cotton: 4200/1400 = 3.000 cumec × 200 = 600.0
  • Wheat: 3100/1800 = 1.722 cumec × 120 = 206.7
  • Rice: 3200/900 = 3.556 cumec × 120 = 426.7
  • Vegetables: 1100/700 = 1.571 cumec × 120 = 188.6

Net requirement at the field = 4,346.9 cumec-days.

Canal losses (15%) and reservoir losses (10%) act in series, so

Gross storage = 4,346.9/(0.85 × 0.90) = 5,682.2 cumec-days.

With 1 cumec-day = 86,400 m³, storage = 5,682.2 × 86,400 = 4.91 × 10⁸ m³.

Required reservoir capacity ≈ 491 Mm³. Overlapping crop seasons could be refined by a mass-curve check, but this is the standard duty-based estimate.

How this answer will be evaluated

What earns full marks: Complete calculations with all checks, clear presentation, correct units, and design verification

Evaluation rubric

Each sub-part is marked on its own, against the marks and word limit printed on the paper.

  1. (a) Design rectangular and circular settling tanks for 20,000 m³/d flow. 20 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Calculate settling zone area using 20 m/d overflow rate
    • Rectangular unit: A = 1,000 m² from Q/SOR, L:W = 3:1 (W = 18.3 m, L = 54.8 m, depth 3.5 m)
    • Determine circular tank diameter (depth 4.0 m)
    • Check retention time, horizontal velocity (13 m/h for one unit, so split into two) and weir overflow rate

    Loses marks

    • Missing design checks for retention time or velocity
    • Incorrect unit conversion or calculation errors
    • Failure to distinguish settling zone from overall dimensions

    Earns more

    • Calculate overall basin dimensions including inlet/outlet zones
    • Show step-by-step substitution of values
    • Verify results against specified limits (3-5 hrs, <10 m/h, 6-10 m³/h/m)

    Extra mark

    • Provide neat labelled sketch of tank cross-sections
  2. (b) Explain why ultimate carbonaceous BOD is typically less than COD. 15 marks

    explain— definition/context → points in order → small example → short close

    Must cover

    • Define BOD and COD measurement principles
    • Identify non-biodegradable organic compounds
    • Explain limitations of biological oxidation
    • Mention specific compounds not oxidized by bacteria

    Loses marks

    • Confusing BOD with DO or other parameters
    • Vague statements without specific chemical reasons
    • Failing to distinguish carbonaceous from total BOD

    Earns more

    • Discuss refractory organic matter
    • Mention toxic substances inhibiting bacteria
    • Reference specific examples of non-biodegradable compounds

    Extra mark

    • Provide quantitative comparison of typical BOD/COD ratios
  3. (c) Calculate reservoir storage capacity for given cropping pattern. 15 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Compute discharge A/D and volume A×B/D for each crop
    • Sum the crop volumes to a net requirement of about 4,347 cumec-days
    • Apply canal (15%) and reservoir (10%) losses in series (divide by 0.85 and by 0.90)
    • Convert to m³ using 1 cumec-day = 86,400 m³ (about 491 Mm³)

    Loses marks

    • Incorrect application of loss percentages
    • Missing crops from calculation
    • Unit errors in area or water volume

    Earns more

    • Show tabular calculation for each crop
    • State V = A×B/D with duty D in ha/cumec
    • Present final answer with appropriate units

    Extra mark

    • Remark that overlapping crop seasons could be checked with a mass curve
What "Solve" is asking you to do

Choose the method, then carry it through to a final answer. Identifying what kind of problem this is and why that method applies is the first thing marked; a correct figure arrived at invisibly earns almost nothing.

Structure that answers it

Given data and what is required → method chosen, with the reason it applies → set-up (equation, circuit, free body, trial balance) → working, step by step → answer with units and any condition of validity

Where marks are lost

Doing the middle steps mentally and writing only the result. In mathematics papers, a further loss comes from giving a decimal where the exact value in surds or fractions was wanted, or from skipping the justification a part explicitly asks for.

All UPSC directive words, compared →

Practice this exact question

Write your answer and it is marked point by point against the model answer above — what you covered, what you missed, what you got wrong.

Evaluate my answer →

More from Civil Engineering 2021 Paper II

Write this answer and get it marked in about 20 seconds

Free account: 5 AI evaluations a month, marked against the rubric above.

Start free

Already have an account? Log in