Civil Engineering 2022 Paper II 50 marks Design

Paper II — Q3

(a) A two-lane State Highway in plain terrain, with cutting section having camber of 2·0%, negotiates a curve of radius 480 m…

(a)

A two-lane State Highway in plain terrain, with cutting section having camber of 2·0%, negotiates a curve of radius 480 m. Design superelevation and explain the process of attaining designed superelevation with the help of neat sketches. 15 marks

(b)
(i)

The following consecutive readings were observed, on a continuously sloping ground, with the help of a 4·0 m staff and a dumpy level. If the reduced level of first point is 99·000 m, calculate the level of last point by entering the readings in level book. Also apply the usual checks. 10 marks 3·815, 2·500, 1·335, 2·980 and 0·800 m

(ii)

The maximum quantity of water to be discharged by the side drains on both sides of a highway section is 1·8 m³/s. Design rectangular side drains for the following conditions. Both drains carry equal discharge. Maximum permissible velocity of flow = 0·8 m/s Roughness coefficient = 0·03 10 marks

(c)

The project of constructing a small road in a rural area consists of various activities as given in the table below. The time (in weeks) and cost (₹ in lakh) required for completion of each activity is also given.

ActivityNormal Time (Weeks)Normal Cost (₹ in lakh)
1-3990
1-212180
2-318210
3-420360
(i)

The construction of road started from 1st January. The project was reviewed after 13 weeks and the following conditions were observed: Activities 1 – 2 and 1 – 3 are completed as originally planned.

(ii)

Activity 2 – 3 is in process and will require 19 more weeks to complete.

(iii)

Activity 3 – 4 has not started.

Based on the above review after 13 weeks, formulate a new project including all activities.

Will the project be completed by 15th August of the same year?

If the project is to be completed in 49 weeks, determine how much activity 3 – 4 is to be crashed and what will be the increase in project cost?

Assume crash cost for activity 3 – 4 is ₹ 450 lakh and crash time is 17 weeks. 15 marks

हिंदी में प्रश्न पढ़ें
(a)

मैदानी भू-भाग में एक दो-लेन का राज्य महामार्ग, कटाई परिछेद में 2·0% कैम्बर के साथ एक 480 m त्रिज्या के वक्र को संचरित करता है । बाह्योथान को अभिकल्पित कीजिए तथा स्वच्छ रेखाचित्रों की सहायता से अभिकल्पित बाह्योथान को प्राप्त करने की प्रक्रिया की व्याख्या कीजिए । 15 अंक

(b)
(i)

एक डम्पी लेवल और 4·0 m स्टाफ की सहायता से निम्नलिखित क्रमिक पाठ्यांक एक सतत ढालु जमीन पर प्राप्त किए गए । यदि प्रथम बिंदु का समानित तल (आर.एल.) 99·000 m है, तो लेवल बुक में पाठ्यांकों की प्रविष्टि करते हुए अंतिम बिंदु के समानित तल की गणना कीजिए । सामान्य जाँचों का भी प्रयोग कीजिए । 10 अंक 3·815, 2·500, 1·335, 2·980 तथा 0·800 m

(ii)

एक महामार्ग परिछेद के दोनों तरफ पार्श्व नालियों से निस्सारित किए जाने वाले पानी की अधिकतम मात्रा 1·8 m³/s है । निम्नलिखित परिस्थितियों के लिए आयताकार पार्श्व नालियों का अभिकल्पन कीजिए । दोनों नालियों का निस्सरण समान है । प्रवाह का अधिकतम अनुज्ञेय वेग = 0·8 m/s रुक्षता गुणांक = 0·03 10 अंक

(c)

ग्रामीण क्षेत्र में एक छोटी सड़क निर्माण की परियोजना के लिए विभिन्न क्रियाएं नीचे दी गई तालिका में दी गई हैं । प्रत्येक क्रिया को पूरा करने के लिए आवश्यक समय (सप्ताह में) तथा लागत (₹ लाख में) भी दी गई है ।

क्रियासामान्य समय (सप्ताह)सामान्य लागत (₹ लाख में)
1-3990
1-212180
2-318210
3-420360
(i)

सड़क निर्माण 1 जनवरी से प्रारंभ हुआ । 13 सप्ताह बाद परियोजना की समीक्षा की गई तथा निम्नलिखित परिस्थितियाँ प्रेक्षित की गईं : क्रियाएं 1-2 तथा 1-3 पूर्ण हो गईं, जैसे मूल-रूप में आयोजित थीं ।

(ii)

क्रिया 2-3 प्रक्रिया में है और पूर्ण होने के लिए 19 सप्ताह और आवश्यक हैं ।

(iii)

क्रिया 3-4 प्रारंभ नहीं हुई है ।

13 सप्ताह के बाद उपर्युक्त समीक्षा के आधार पर, सभी क्रियाओं को शामिल करते हुए एक नई परियोजना बनाइए ।

क्या परियोजना उसी वर्ष के 15 अगस्त तक पूरी हो जाएगी ?

यदि परियोजना को 49 सप्ताह में पूरा करना है, तो निर्धारित कीजिए कि क्रिया 3-4 को कितना क्रैश किया जाना है तथा परियोजना लागत में कितनी वृद्धि होगी ?

क्रिया 3-4 के लिए क्रैश लागत ₹ 450 लाख तथा क्रैश समय 17 सप्ताह मान लीजिए । 15 अंक

Q3 of the 2022 UPSC Mains Civil Engineering Paper II, as printed
The question as printed in the 2022 Civil Engineering paper

The figure this question refers to, in words

The question paper is a scan and the diagram did not survive as text. This is the figure as read from the original page — every component, value and label — so the question can be worked from the text below.

(c) Table with columns: Activity, Normal Time (Weeks), Normal Cost (₹ in lakh). Rows: 1-3, 9, 90; 1-2, 12, 180; 2-3, 18, 210; 3-4, 20, 360.

Model answer

Drafted with AI by UPSC Answer Check against this question's marking rubric, to the expected length. UPSC does not publish answers for Mains — this is one way to score well, not an official key. How we build rubrics and answers.

(a) Superelevation for a 480 m curve on a two-lane State Highway

Design speed. For a State Highway in plain terrain IRC:73 gives a ruling design speed of 100 km/h (minimum 80 km/h). Use V = 100 km/h.

Superelevation. IRC provides superelevation to balance the centrifugal force of 75 % of the design speed, neglecting friction:

  • e = (0.75V)²/(127R) = V²/(225R) = 100²/(225 × 480) = 0.093
  • This exceeds the IRC maximum of 7 % for plain terrain, so e = 0.07 is adopted.

Check of side friction at the full design speed.

  • f = V²/(127R) − e = 100²/(127 × 480) − 0.07 = 0.164 − 0.07 = 0.094
  • This is below the permissible 0.15, so e = 7 % is adequate and the speed need not be restricted. Provide superelevation of 7 %.

Length of transition (IRC:73, larger of three criteria). Pavement width W = 7.0 m. Extra widening at R = 480 m, W_e = nl²/2R + V/(9.5√R) = 2 × 6²/960 + 100/(9.5 × 21.9) ≈ 0.56 m, so W + W_e ≈ 7.56 m.

  • Rate of change of centrifugal acceleration: C = 80/(75 + V) = 0.457 m/s³, L_s = 0.0215V³/(CR) = 0.0215 × 100³/(0.457 × 480) = 98 m
  • Rate of introducing superelevation, 1 in 150 for plain terrain, rotating about the inner edge: L_s = e N (W + W_e) = 0.07 × 150 × 7.56 = 79 m
  • Empirical formula for plain terrain: L_s = 2.7V²/R = 2.7 × 100²/480 = 56 m
  • Provide a transition of 100 m, over which superelevation is introduced.

Attaining the superelevation in a cutting. In a cutting the inner edge is not lowered, because that would put the inner side drain and the pavement edge below the formation and spoil drainage. The pavement is therefore rotated about the inner edge:

  1. Eliminating the crown. At the start of the transition the section has 2 % camber. The outer half is raised about the crown until it is level, and then until it slopes towards the inside at 2 %, so the whole carriageway has a uniform 2 % cross-fall towards the inner edge.
  2. Rotating to full superelevation. The whole pavement is then rotated about the inner edge, raising the centre line and the outer edge, until the cross-slope reaches 7 % at the start of the circular curve.
  3. The outer edge rises at no more than 1 in 150 of the transition length, and the profiles of the outer edge, centre line and inner edge are run out along the transition.
Diagram: Attaining superelevation by rotation about the inner edge

(b)(i) Level book for the five readings

On rising ground the readings fall along the line until the staff can no longer be read, so the instrument is shifted after 1.335 (a foresight on a change point) and 2.980 is the backsight from the new position.

  • Point 1: BS 3.815, HI = 99.000 + 3.815 = 102.815, RL 99.000
  • Point 2: IS 2.500, RL = 102.815 − 2.500 = 100.315
  • Point 3 (change point): FS 1.335, RL = 102.815 − 1.335 = 101.480, then BS 2.980, new HI = 101.480 + 2.980 = 104.460
  • Point 4: FS 0.800, RL = 104.460 − 0.800 = 103.660

Checks.

  • ΣBS − ΣFS = (3.815 + 2.980) − (1.335 + 0.800) = 6.795 − 2.135 = 4.660 m
  • Last RL − first RL = 103.660 − 99.000 = 4.660 m
  • Rise and fall: rises of 1.315, 1.165 and 2.180 m, total 4.660 m, with no falls All three agree, so the arithmetic is correct. RL of the last point = 103.660 m.

(b)(ii) Rectangular side drains

  • Discharge per drain Q = 1.8/2 = 0.90 m³/s
  • With V limited to 0.8 m/s, A = Q/V = 0.90/0.8 = 1.125 m²
  • For the most economical rectangular section b = 2y and R = y/2: 2y² = 1.125, so y = 0.75 m, b = 1.50 m, R = 0.375 m
  • Manning equation V = (1/n) R^(2/3) S^(1/2), so 0.8 = (1/0.03) × 0.375^(2/3) × S^(1/2) = 17.33 S^(1/2), giving S = 0.00213, about 1 in 470

Provide rectangular drains 1.50 m wide with 0.75 m flow depth on each side, laid at about 1 in 470, with a freeboard of about 0.15 m (total depth 0.90 m).

(c) Updating the road project after 13 weeks

Original network. Paths: 1–2–3–4 = 12 + 18 + 20 = 50 weeks (critical), and 1–3–4 = 9 + 20 = 29 weeks. Normal cost = 90 + 180 + 210 + 360 = ₹ 840 lakh.

Updated network at week 13.

  • 1–2 and 1–3 are complete (1–2 finished at week 12, 1–3 at week 9).
  • 2–3 started at week 12 and needs 19 more weeks from week 13, so it ends at week 32 (its duration has grown from 18 to 20 weeks).
  • 3–4 can start only at week 32 and takes 20 weeks, ending at week 52.
  • The new network from week 13 is 2–3 (remaining 19 weeks) followed by 3–4 (20 weeks), and this is the critical path.
Diagram: Updated time-scaled network for the rural road project

Completion by 15 August? 15 August is the 227th day of the year, about 32.4 weeks after 1 January. The project now needs 52 weeks, ending around the end of December, so it will not be completed by 15 August. Even the original 50-week plan could not have met that date.

Crashing to 49 weeks.

  • Required reduction = 52 − 49 = 3 weeks, and only 3–4 remains to be crashed.
  • 3–4 can be shortened from 20 to 17 weeks, exactly the 3 weeks needed.
  • Cost slope = (450 − 360)/(20 − 17) = ₹ 30 lakh per week.
  • Crash 3–4 by 3 weeks. Increase in project cost = 3 × 30 = ₹ 90 lakh, raising the total from ₹ 840 lakh to ₹ 930 lakh (assuming the delayed activity 2–3 costs no more than planned).

How this answer will be evaluated

Framework: Civil Engineering Paper 2: Design/Analysis/Calculation

What earns full marks: Complete calculations with code references, neat sketches, and all checks applied

Evaluation rubric

Each sub-part is marked on its own, against the marks and word limit printed on the paper.

  1. (a) Design superelevation for 480m curve and explain transition process. 15 marks

    explain— definition/context → points in order → small example → short close

    Must cover

    • Calculate superelevation using IRC formula
    • Transition length as the largest of the centrifugal-acceleration, superelevation-rate and empirical criteria (≈ 98 m, provide 100 m)
    • Describe transition from normal to full superelevation
    • Provide neat sketches of transition

    Loses marks

    • Missing transition curve length calculation
    • No sketches of superelevation transition
    • Ignoring camber in superelevation calc

    Earns more

    • Checks friction f = V²/127R − e ≤ 0.15 at the full design speed
    • Calculate rate of change of camber
    • Show spiral transition details

    Extra mark

    • Cites IRC:73 / IRC:38 clauses for design speed, e_max and transition length
    • Include numerical example of camber change
  2. (b)(i) Calculate last point level using level book method. 10 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Enter readings in level book format
    • Calculate intermediate levels correctly
    • Apply arithmetic checks on readings
    • State final reduced level with units

    Loses marks

    • Missing level book format
    • Arithmetic errors in level calculations
    • No final reduced level stated

    Earns more

    • Show height of instrument calculations
    • Verify sum of BS equals sum of FS
    • Identify change points in readings

    Extra mark

    • Include error correction if applicable
    • Show staff reading verification
  3. (b)(ii) Design rectangular side drains for 1.8 m³/s discharge. 10 marks

    calculate— given → formula → substitution → result with units → interpretation

    Must cover

    • Apply Manning's equation for design
    • Calculate required cross-sectional area
    • Determine hydraulic radius and slope
    • Verify velocity within 0.8 m/s limit

    Loses marks

    • Velocity exceeds 0.8 m/s limit
    • Missing Manning's equation application
    • No hydraulic radius calculation

    Earns more

    • Show Manning's n=0.03 application
    • Calculate wetted perimeter
    • Adds a freeboard to the flow depth

    Extra mark

    • Include freeboard calculation
    • Show velocity distribution check
  4. (c) Formulate new project schedule and determine crash requirements. 15 marks

    analyse— intro → causes → effects → stakeholders/linkages → way forward

    Must cover

    • Update activity times after 13 weeks
    • Calculate new project duration
    • Determine crash amount for activity 3-4
    • Calculate cost increase for crashing

    Loses marks

    • Missing new project formulation
    • No crash cost calculation
    • Incorrect critical path identification

    Earns more

    • Show critical path identification
    • Calculate crash cost per week
    • Verify 49-week completion feasibility
    • Show date calculation for Aug 15

    Extra mark

    • Include Gantt chart update
    • Show float calculations
What "Design" is asking you to do

Produce a specification that meets the given brief and demonstrate that it does. In civil and electrical papers the design is incomplete until it is expressed in buildable numbers — diameter, spacing, section, component value — and checked back against every limit stated.

Structure that answers it

Requirements and permissible values listed → code clause or design basis adopted → proportioning calculations → the specification in final dimensions → check against each requirement → sketch

Where marks are lost

Stopping at a required area or a required value without converting it into the bar size, spacing or component actually provided. The provided-against-required comparison and the serviceability or stability check are separately marked and routinely left out.

All UPSC directive words, compared →

Practice this exact question

Write your answer and it is marked point by point against the model answer above — what you covered, what you missed, what you got wrong.

Evaluate my answer →

More from Civil Engineering 2022 Paper II

Write this answer and get it marked in about 20 seconds

Free account: 5 AI evaluations a month, marked against the rubric above.

Start free

Already have an account? Log in