Civil Engineering 2022 Paper II 50 marks Design

Q3

(a) A two-lane State Highway in plain terrain, with cutting section having camber of 2·0%, negotiates a curve of radius 480 m. Design superelevation and explain the process of attaining designed superelevation with the help of neat sketches. 15 marks (b) (i) The following consecutive readings were observed, on a continuously sloping ground, with the help of a 4·0 m staff and a dumpy level. If the reduced level of first point is 99·000 m, calculate the level of last point by entering the readings in level book. Also apply the usual checks. 10 marks 3·815, 2·500, 1·335, 2·980 and 0·800 m (ii) The maximum quantity of water to be discharged by the side drains on both sides of a highway section is 1·8 m³/s. Design rectangular side drains for the following conditions. Both drains carry equal discharge. Maximum permissible velocity of flow = 0·8 m/s Roughness coefficient = 0·03 10 marks (c) The project of constructing a small road in a rural area consists of various activities as given in the table below. The time (in weeks) and cost (₹ in lakh) required for completion of each activity is also given. | Activity | Normal Time (Weeks) | Normal Cost (₹ in lakh) | |----------|---------------------|-------------------------| | 1-3 | 9 | 90 | | 1-2 | 12 | 180 | | 2-3 | 18 | 210 | | 3-4 | 20 | 360 | The construction of road started from 1st January. The project was reviewed after 13 weeks and the following conditions were observed: (i) Activities 1 – 2 and 1 – 3 are completed as originally planned. (ii) Activity 2 – 3 is in process and will require 19 more weeks to complete. (iii) Activity 3 – 4 has not started. Based on the above review after 13 weeks, formulate a new project including all activities. Will the project be completed by 15th August of the same year? If the project is to be completed in 49 weeks, determine how much activity 3 – 4 is to be crashed and what will be the increase in project cost? Assume crash cost for activity 3 – 4 is ₹ 450 lakh and crash time is 17 weeks. 15 marks

हिंदी में प्रश्न पढ़ें

(a) मैदानी भू-भाग में एक दो-लेन का राज्य महामार्ग, कटाई परिछेद में 2·0% कैम्बर के साथ एक 480 m त्रिज्या के वक्र को संचरित करता है । बाह्योथान को अभिकल्पित कीजिए तथा स्वच्छ रेखाचित्रों की सहायता से अभिकल्पित बाह्योथान को प्राप्त करने की प्रक्रिया की व्याख्या कीजिए । 15 अंक (b) (i) एक डम्पी लेवल और 4·0 m स्टाफ की सहायता से निम्नलिखित क्रमिक पाठ्यांक एक सतत ढालु जमीन पर प्राप्त किए गए । यदि प्रथम बिंदु का समानित तल (आर.एल.) 99·000 m है, तो लेवल बुक में पाठ्यांकों की प्रविष्टि करते हुए अंतिम बिंदु के समानित तल की गणना कीजिए । सामान्य जाँचों का भी प्रयोग कीजिए । 10 अंक 3·815, 2·500, 1·335, 2·980 तथा 0·800 m (ii) एक महामार्ग परिछेद के दोनों तरफ पार्श्व नालियों से निस्सारित किए जाने वाले पानी की अधिकतम मात्रा 1·8 m³/s है । निम्नलिखित परिस्थितियों के लिए आयताकार पार्श्व नालियों का अभिकल्पन कीजिए । दोनों नालियों का निस्सरण समान है । प्रवाह का अधिकतम अनुज्ञेय वेग = 0·8 m/s रुक्षता गुणांक = 0·03 10 अंक (c) ग्रामीण क्षेत्र में एक छोटी सड़क निर्माण की परियोजना के लिए विभिन्न क्रियाएं नीचे दी गई तालिका में दी गई हैं । प्रत्येक क्रिया को पूरा करने के लिए आवश्यक समय (सप्ताह में) तथा लागत (₹ लाख में) भी दी गई है । | क्रिया | सामान्य समय (सप्ताह) | सामान्य लागत (₹ लाख में) | |--------|----------------------|---------------------------| | 1-3 | 9 | 90 | | 1-2 | 12 | 180 | | 2-3 | 18 | 210 | | 3-4 | 20 | 360 | सड़क निर्माण 1 जनवरी से प्रारंभ हुआ । 13 सप्ताह बाद परियोजना की समीक्षा की गई तथा निम्नलिखित परिस्थितियाँ प्रेक्षित की गईं : (i) क्रियाएं 1-2 तथा 1-3 पूर्ण हो गईं, जैसे मूल-रूप में आयोजित थीं । (ii) क्रिया 2-3 प्रक्रिया में है और पूर्ण होने के लिए 19 सप्ताह और आवश्यक हैं । (iii) क्रिया 3-4 प्रारंभ नहीं हुई है । 13 सप्ताह के बाद उपर्युक्त समीक्षा के आधार पर, सभी क्रियाओं को शामिल करते हुए एक नई परियोजना बनाइए । क्या परियोजना उसी वर्ष के 15 अगस्त तक पूरी हो जाएगी ? यदि परियोजना को 49 सप्ताह में पूरा करना है, तो निर्धारित कीजिए कि क्रिया 3-4 को कितना क्रैश किया जाना है तथा परियोजना लागत में कितनी वृद्धि होगी ? क्रिया 3-4 के लिए क्रैश लागत ₹ 450 लाख तथा क्रैश समय 17 सप्ताह मान लीजिए । 15 अंक

Directive word: Design

This question asks you to design. The directive word signals the depth of analysis expected, the structure of your answer, and the weight of evidence you must bring.

See our UPSC directive words guide for a full breakdown of how to respond to each command word.

How this answer will be evaluated

Approach

Design requires systematic problem-solving with calculations and sketches. Allocate ~30% time to part (a) superelevation design with rotation diagrams, ~35% to part (b) numerical problems (levelling and drain design), and ~35% to part (c) CPM crashing analysis. Begin with clear problem statements, show all formulae with IRC/IS codes, present stepwise calculations, and conclude with practical feasibility checks.

Key points expected

  • Part (a): Calculate superelevation for R=480m using IRC formula e=V²/225R, check against maximum 7% and 10% limits, apply ruling speed of 80 kmph for State Highway, and explain rotation about centre-line with inner edge depressed and outer edge raised
  • Part (a): Draw three neat sketches showing (i) normal camber section, (ii) transition start with outer edge raised, (iii) full superelevation with rotated section
  • Part (b)(i): Enter readings in standard level book format with BS, IS, FS columns, calculate rises and falls, verify ΣBS-ΣFS=Last RL-First RL=ΣRise-ΣFall, determine final RL
  • Part (b)(ii): Apply Manning's equation V=(1/n)R^(2/3)S^(1/2) for rectangular drain, assume b=2y or given proportions, calculate dimensions for Q=0.9 m³/s per drain, check velocity < 0.8 m/s
  • Part (c): Draw original network, identify critical path 1-2-3-4 (50 weeks), formulate revised network after 13 weeks with remaining durations, calculate new completion date and compare with 15th August (32 weeks from 1st Jan)
  • Part (c): Determine crash requirement for 49-week completion, calculate cost slope for activity 3-4, find crash weeks needed and additional cost

Evaluation rubric

DimensionWeightMax marksExcellentAveragePoor
Concept correctness20%10Correctly applies IRC:38 for superelevation limits and rotation methods; uses standard levelling terminology (BS, FS, IS, HI) correctly; applies Manning's equation with appropriate hydraulic radius for rectangular sections; constructs accurate CPM network with proper critical path identification and crashing logicUses correct basic formulae but with minor errors in IRC code application or hydraulic radius definition; network drawn but critical path identification may have errors; understands levelling procedure but confuses rise/fall method with height of instrumentFundamental conceptual errors such as using wrong superelevation formula, treating Manning's n incorrectly, or completely misunderstanding CPM methodology with wrong activity dependencies
Numerical accuracy20%10All calculations precise: superelevation value with proper limiting checks, levelling arithmetic with exact RL to 3 decimals, drain dimensions satisfying Q and V constraints, CPM time analysis with correct crash cost computation (₹90 lakh per week for activity 3-4)Correct methodology with minor arithmetic slips in one or two parts; final answers slightly off but approach verifiable; rounding errors in significant figuresMajor calculation errors in multiple parts, wrong unit conversions, or completely incorrect final answers without working checks
Diagram quality20%10Three clear superelevation sketches showing rotation stages with dimensions and slopes; neat level book tabulation with proper columns; network diagram with nodes, activities, durations, and critical path highlighted; drain cross-section with flow depth and freeboardDiagrams present but lacking clarity or incomplete annotations; sketches show concept but missing key dimensions; network drawn but without proper activity-on-arrow or activity-on-node conventionsMissing essential diagrams, illegible sketches without labels, or no attempt at network representation despite question requirements
Step-by-step derivation20%10Every formula stated before substitution (e=V²/225R, e_max=0.07, Manning's equation, cost slope formula); clear logical flow from given data to solution; arithmetic checks shown for levelling; crashing steps enumerated with time-cost trade-offsFormulae mentioned but derivation skips some intermediate steps; working shown but not always logically sequenced; checks mentioned but not fully executedNo formulae stated, jumps to final answers, or working so disorganized that verification is impossible
Practical interpretation20%10Interprets superelevation attainment for construction sequencing; discusses drain freeboard and maintenance access; clearly states project cannot meet 15th August deadline (requires 51 weeks vs 32 available); identifies minimum 49-week completion needs 2-week crash on activity 3-4 at ₹180 lakh additional cost; suggests practical alternativesStates conclusions but with limited practical context; mentions deadline issues but calculation errors affect validity; cost implications stated without sensitivity analysisNo interpretation of results, ignores deadline feasibility question, or provides conclusions contradicted by own calculations

Practice this exact question

Write your answer, then get a detailed evaluation from our AI trained on UPSC's answer-writing standards. Free first evaluation — no signup needed to start.

Evaluate my answer →

More from Civil Engineering 2022 Paper II