Civil Engineering

UPSC Civil Engineering 2023 — Paper II

All 8 questions from UPSC Civil Services Mains Civil Engineering 2023 Paper II (400 marks total). Every stem reproduced in full, with directive-word analysis, marks, word limits, and answer-approach pointers.

8Questions
400Total marks
2023Year
Paper IIPaper

Topics covered

Civil Engineering - Construction Materials and Surveying (1)Project Management and Railway Engineering (1)Traffic surveys, tunnel surveying, bulking of sand (1)Depreciation, dampness in buildings, flexible pavement design (1)Hydrology and water quality (1)Groundwater hydrology and water supply (1)Environmental and Water Resources Engineering (1)Irrigation, Environmental and Air Pollution Engineering (1)

A

Q1
50M Compulsory explain Civil Engineering - Construction Materials and Surveying

(a) What are the approximate limits of chemical (oxide) composition in hydraulic cement ? Also state the function of oxides in brief. (10 marks) (b) (i) Explain with neat sketches, how Work Breakdown Structure can be defined with respect to Construction Project Management. (ii) With an example, explain how the work breakdown structure can be classified. (10 marks) (c) What do you understand by workability of concrete ? Write the procedure for any one measurement method available to check the workability of concrete. (10 marks) (d) A 100 km length railway line is to be constructed for doubling the existing track. Calculate the quantity of track material required to construct the track. Consider the length of rail as 13 m, density of sleepers as (n + 4) and width of sleeper as 250 mm. (10 marks) (e) The Fore Bearing of side AB of regular hexagonal polygon ABCDEFA in whole circle bearing system is 120°. Find the Fore Bearings and Back Bearings of all the other sides. Also find the bearings of line BE and BF. (10 marks)

हिंदी में पढ़ें

(a) जलीय सीमेंट के रासायनिक (ऑक्साइड) संयोजन की सन्निकट सीमाएं क्या हैं ? ऑक्साइडों के कार्यों का भी संक्षेप में वर्णन कीजिए। (10 अंक) (b) (i) निर्माण परियोजना प्रबंधन की दृष्टि से, स्वच्छ चित्रों की सहायता से व्याख्या कीजिए कि कार्य भंग संरचना को कैसे परिभाषित किया जा सकता है। (ii) एक उदाहरण के द्वारा व्याख्या कीजिए कि कार्य भंग संरचना को कैसे वर्गीकृत किया जा सकता है। (10 अंक) (c) कंक्रीट की सुकार्यता से आप क्या समझते हैं ? कंक्रीट की सुकार्यता की जाँच के लिए उपलब्ध किसी एक मापन विधि की प्रक्रिया का वर्णन कीजिए। (10 अंक) (d) वर्तमान में मौजूद एक रेलपथ के दोहरीकरण के लिए एक 100 km लम्बी रेलवे लाइन का निर्माण करना है। रेलपथ के निर्माण के लिए आवश्यक रेलपथ सामग्री की गणना कीजिए। रेल की लम्बाई 13 m, स्लीपरों का घनत्व (n + 4) एवं स्लीपर की चौड़ाई 250 mm लीजिए। (10 अंक) (e) एक नियमित षट्कोणीय बहुभुज ABCDEFA की भुजा AB का अग्रदिक्मान पूर्णदिक्मान पद्धति में 120° है। अन्य सभी भुजाओं के अग्रदिक्मान एवं पश्चदिक्मान ज्ञात कीजिए। रेखा BE एवं BF के दिक्मान भी ज्ञात कीजिए। (10 अंक)

Answer approach & key points

(a) enumerate: list the items in order > one line each > no commentary | (b) explain: definition/context > points in order > small example > short close | (c) describe: define > structure or process in order > labelled diagram > significance | (d) calculate: given > formula > substitution > result with units > interpretation | (e) calculate: given > formula > substitution > result with units > interpretation Full marks: All parts answered with correct method, units, and sketches where required.

  • CaO 60–67%, SiO₂ 17–25%, Al₂O₃ 3–8%, Fe₂O₃ 0.5–6%
  • MgO 0.1–4%, SO₃ 1–3%, alkalis 0.4–1.3%
  • CaO and SiO₂ give strength through C₃S and C₂S
  • Al₂O₃ gives quick setting; SO₃ controls setting; excess MgO and free lime cause unsoundness
  • WBS is a hierarchical deliverable-based breakdown of project scope
  • Levels: project, deliverables, work packages, activities
  • 100% rule and ownership of work packages
  • Classification by phase, system, location or organisation with a metro example
  • Definition: ease of mixing, placing and compacting without segregation
  • Factors: water–cement ratio, aggregate, admixtures
  • Slump cone 300 × 200 × 100 mm, three layers, 25 tamps with 16 mm rod
  • Lift in 5–10 s and measure the subsidence
  • Two rails per track: 2 × 100 000/13 ≈ 15 385 rails
  • Sleepers: (13 + 4) = 17 per rail ≈ 1,30,770
  • Fish plates ≈ 30 770 and fish bolts ≈ 61 540
  • Sleeper fittings ≈ 5,23,080; ballast not computable
  • Step of +60° per side for a clockwise traverse
  • Fore bearings 120, 180, 240, 300, 0, 60 and back bearings 300, 0, 60, 120, 180, 240
  • BE = 240° (parallel to CD)
  • BF = 270°
Q2
50M solve Project Management and Railway Engineering

(a) For a project consisting of several activities, the allotted time and the dependencies of the activities are presented below. The activities are: P (5 days, no predecessor); Q (4 days, no predecessor); R (6 days, predecessor Q); S (5 days, predecessor P); T (7 days, predecessor P); U (4 days, predecessors T and R). (i) Prepare a network and mark critical path in it. (ii) Calculate Float, Earliest start, Earliest finish, Latest start and Latest finish times. (20 marks) (b) Trains of different speeds are to be run on a 2° curve on a broad gauge. The average speed of trains to be run on the track is 80 kmph. Calculate the value of equilibrium cant. Also calculate the maximum permissible speed on the track allowing the maximum cant deficiency. (15 marks) (c) (i) An aircraft flew at the altitude of 5000 m above the mean sea level. Two consecutive photographs were taken with the camera of focal length 300 mm on the flat ground having elevation of 2000 m above mean sea level. The longitudinal overlap is 65% and photograph print size is 300 mm × 300 mm. Calculate the scale of the photograph and distance between the two consecutive exposure stations. (5 marks) (ii) What is spectral reflectance curve ? Explain its significance in Remote Sensing. (10 marks)

हिंदी में पढ़ें

(क) विभिन्न क्रियाओं से बनी एक परियोजना के लिए क्रियाओं की आवंटित समय अवधि और पराश्रयता को नीचे दर्शाया गया है । क्रियाएँ: P (5 दिन, कोई पूर्ववर्ती नहीं); Q (4 दिन, कोई पूर्ववर्ती नहीं); R (6 दिन, पूर्ववर्ती Q); S (5 दिन, पूर्ववर्ती P); T (7 दिन, पूर्ववर्ती P); U (4 दिन, पूर्ववर्ती T और R)। (i) एक जाल का निर्माण कीजिए और उसमें क्रांतिक पथ को दर्शाइए । (ii) प्लव (फ्लोट), यथाशीघ्र प्रारंभ, यथाशीघ्र समाप्ति, यथाविलम्बित प्रारंभ और यथाविलम्बित समाप्ति समयों की गणना कीजिए । (20 अंक) (ख) एक बड़ी लाइन पर 2° वक्र पर विभिन्न गति की रेलगाड़ियों को चलाया जाना है । रेलपथ पर चलाई जाने वाली रेलगाड़ियों की औसत गति 80 kmph है । संतुलन आनति (कैन्ट) के मान की गणना कीजिए । अधिकतम आनति न्यूनता की अनुमति के साथ रेलपथ पर अधिकतम अनुज्ञेय गति की गणना भी कीजिए । (15 अंक) (ग) (i) एक वायुयान माध्य समुद्र तल से 5000 m की ऊँचाई पर उड़ा । एक समतल मैदान, जो माध्य समुद्र तल से 2000 m की ऊँचाई पर है, से एक कैमरा जिसकी फोकस दूरी 300 mm है, से दो क्रमागत तस्वीरें ली गईं । अनुदैर्ध्य अतिव्यापन 65% है एवं तस्वीर का प्रिन्ट आमाप 300 mm × 300 mm है । तस्वीर के स्केल की गणना कीजिए । दोनों क्रमागत उद्भासन स्टेशनों के बीच की दूरी बताइए । (5 अंक) (ii) वर्णक्रमीय परावर्तकता वक्र क्या है ? सुदूर संवेदन में इसकी सार्थकता की व्याख्या कीजिए । (10 अंक)

Answer approach & key points

(a) calculate: given > formula > substitution > result with units > interpretation | (b) calculate: given > formula > substitution > result with units > interpretation | (c(i)) calculate: given > formula > substitution > result with units > interpretation | (c(ii)) explain: definition/context > points in order > small example > short close Full marks: All parts fully answered with correct formulas, units, and clear diagrams; no calculation errors; code references where applicable.

  • Dependencies: P→S, P→T, Q→R, T and R→U
  • Forward pass gives 16 days
  • Backward pass and float: P0, Q2, R2, S6, T0, U0
  • Critical path P → T → U
  • R = 1750/D = 875 m
  • e = GV²/127R = 100.8 mm with G = 1750 mm
  • Maximum cant deficiency 75 mm for BG
  • V_max ≈ 105.7 km/h
  • H − h = 3000 m
  • Scale = f/(H − h) = 1:10 000
  • Ground coverage 3000 m
  • Air base = 0.35 × 3000 = 1050 m
  • Reflectance vs wavelength curve is the spectral signature
  • Vegetation, water and soil differ in shape
  • Helps identify features and classify land cover
  • Guides sensor bands and indices such as NDVI
Q3
50M solve Traffic surveys, tunnel surveying, bulking of sand

(a) (i) Explain any two traffic surveys carried out to decide the geometric design features of a road. (5 marks) (ii) The relationship between speed and density for a given section of road was found to be v = 100 – 1·2 k, where v is speed in kmph and k is the density in vehicles per km. Calculate the speed and density in which maximum flow could occur. Also draw the speed-density, speed-flow and flow-density diagrams indicating critical values. (15 marks) (b) Starting from ground point A having elevation of 100·500 m, levels from points B to F were taken inside a tunnel. The points B to F were marked in the ceiling of the tunnel keeping the staff inverted. The following staff readings (m) were observed during the survey. Back sight at A, B, C, D, E: 1.234, 1.345, 1.730, 2.056, 2.156. Foresight at B, C, D, E, F: 1.782, 1.830, 2.000, 2.340, 2.780. Calculate the levels of all the points marked inside the tunnel. Also apply the regular checks for calculations. (15 marks) (c) Explain in brief (with neat sketches), the Phenomenon of Bulking of Sand. How does bulking of sand affect the concrete mix ? (15 marks)

हिंदी में पढ़ें

(a) (i) एक सड़क के ज्यामितीय अभिकल्पन लक्षणों का निर्णय लिए जाने के लिए किए जाने वाले किन्हीं दो यातायात सर्वेक्षणों की व्याख्या कीजिए । (5 अंक) (ii) एक सड़क के दिए गए खंड के लिए गति एवं घनत्व के बीच का सम्बन्ध v = 100 – 1·2 k पाया गया, जहाँ v गति, kmph में है और k घनत्व जो वाहन प्रति किलोमीटर में है । उस गति एवं घनत्व की गणना कीजिए जिस पर अधिकतम प्रवाह हो सके । साथ ही क्रांतिक मानों को दर्शित करते हुए गति-घनत्व, गति-प्रवाह एवं प्रवाह-घनत्व आरेखों को आरेखित कीजिए । (15 अंक) (b) 100·500 m ऊँचाई के जमीन बिन्दु A से आरम्भ करते हुए एक सुरंग के अन्दर बिन्दु B से F तक लेवल लिए गए । स्टाफ को उल्टा रखते हुए, B से F तक बिन्दुओं को सुरंग की अन्तःछद (सीलिंग) पर चिह्नित किया गया । सर्वेक्षण के दौरान निम्नलिखित स्टाफ पाठ्यांक (m) प्रेक्षित किए गए । पश्चावलोकन A, B, C, D, E पर: 1.234, 1.345, 1.730, 2.056, 2.156। अग्रावलोकन B, C, D, E, F पर: 1.782, 1.830, 2.000, 2.340, 2.780। सुरंग के अन्दर चिह्नित सभी बिन्दुओं के समानीत तलों की गणना कीजिए । गणनाओं के लिए सामान्य जाँचों का भी प्रयोग कीजिए । (15 अंक) (c) बालू के फूलने की प्रक्रिया की संक्षेप में (स्वच्छित्रों की सहायता से) व्याख्या कीजिए । बालू का फूलना कंक्रीट मिक्स को कैसे प्रभावित करता है ? (15 अंक)

Answer approach & key points

Framework: null. (a(i)) explain: definition/context > points in order > small example > short close | (a(ii)) calculate: given > formula > substitution > result with units > interpretation | (b) calculate: given > formula > substitution > result with units > interpretation | (c) explain: definition/context > points in order > small example > short close Full marks: Complete working, correct values, all diagrams, checks applied

  • Traffic volume survey: counts by type, direction and time
  • Volume fixes lanes, width and junction layout
  • Speed survey: spot speeds and 85th percentile speed
  • Speed fixes design speed, curves, sight distance
  • q = 100k − 1.2k²; dq/dk = 0 gives k = 41.67 veh/km
  • Critical speed 50 km/h and q_max = 2083 veh/h
  • v_f = 100 km/h and k_j = 83.3 veh/km
  • Three diagrams with the critical point marked
  • Ceiling readings on an inverted staff are negative
  • HI = RL + BS; RL = HI − FS with signs kept
  • B 103.516, C 104.001, D 104.271, E 104.555, F 105.179
  • ΣBS − ΣFS = 4.679 = last RL − first RL
  • Moisture film and surface tension push grains apart
  • Peak bulking at about 4–6% moisture and zero at saturation
  • Volume batching gives less sand and a harsh mix
  • Batch by weight or correct the volume and adjust water
Q4
50M calculate Depreciation, dampness in buildings, flexible pavement design

(a) A machine was purchased for ₹4,50,000 on 1st January 2001 and erection and installation work costed ₹80,000. The same machine is replaced by a new one on 31st December 2020. If the scrap value was estimated at ₹1,50,000 (i) What should be the rate of depreciation fund on 15th June 2010 ? (ii) If after 12 years of running, some assemblies are replaced and the replacement cost is ₹1,50,000, what will be the new rate of depreciation ? (20 marks) (b) What is dampness in a building ? What are the main causes of dampness and what are the remedies being suggested for making a building damp-proof ? (15 marks) (c) A flexible pavement has been designed for two lane single carriageway of width 7 m with the following data : (i) Commercial vehicle per day in each direction = 750 (as on 31.03.2018) (ii) Date of completion of construction = 31.03.2020 (iii) Rate of traffic growth = 10% per annum (iv) Design life = 10 years (v) Vehicle damage factor = 2·0 (vi) Lane distribution factor (LDF) for 2-lane single carriageway road = 0·75 (vii) LDF of 4-lane dual carriageway road = 0·75 in each direction Due to some issues, starting of construction got delayed and work started on 01.04.2023. In the meantime government has decided to develop the road as four lane dual carriageway. Considering the same design data as planned earlier, calculate the new design life of the project. Assume any additional data required for the design suitably. (15 marks)

हिंदी में पढ़ें

(a) एक मशीन को 01 जनवरी, 2001 में ₹4,50,000 में खरीदा गया एवं उसके उत्थापन एवं संस्थापन में ₹80,000 खर्च हुआ । 31 दिसम्बर, 2020 को इस मशीन को एक नई मशीन से बदला गया । यदि इसका शेष मूल्य ₹1,50,000 आकलित किया गया तो (i) 15 जून 2010 को मूल्य ह्रास निधि की दर क्या होनी चाहिए ? (ii) यदि 12 साल काम करने के बाद, इसके कुछ कलपुर्जे बदले गए और बदलने की कीमत ₹1,50,000 हो तो नया मूल्य ह्रास दर क्या होगा ? (20 अंक) (b) एक भवन में सीलन क्या होती है ? सीलन होने के मुख्य कारण क्या हैं, एवं एक भवन को सीलनरोधी बनाने के लिए क्या उपचार सुझाए जाते हैं ? (15 अंक) (c) 7 m चौड़े द्वि-मार्गी एकल यानमार्ग के लिए एक नम्य कुंटिटम की अभिकल्पना निम्नलिखित आंकड़ों के लिए की गई है । (i) वाणिज्यिक वाहन प्रतिदिन, प्रत्येक दिशा में = 750 (as on 31.03.2018) को (ii) निर्माण के पूर्ण होने की तिथि = 31.03.2020 (iii) ट्रैफिक वृद्धि की दर = 10% प्रति वर्ष (iv) अभिकल्प काल = 10 वर्ष (v) वाहन क्षति गुणक = 2·0 (vi) द्वि-मार्गी एकल यानमार्ग सड़क के लिए मार्ग वितरण गुणक (एल डी एफ) = 0·75 (vii) चतुर्मार्गी यानमार्ग सड़क के लिए एल डी एफ = 0·75 प्रत्येक दिशा में कुछ कारणों से निर्माण कार्य के शुरू होने में देर हुई और कार्य 01.04.2023 को आरम्भ हुआ । इसी बीच में सरकार सड़क को चतुर्मार्गी दोहरा यानमार्ग के रूप में विकसित करने का निर्णय लेती है । पूर्व में आयोजित आंकड़ों को ध्यान में रखते हुए, परियोजना के नए अभिकल्प काल की गणना कीजिए । अभिकल्पना के लिए आवश्यक अतिरिक्त आंकड़े उपयुक्त रूप से मान लीजिए । (15 अंक)

Answer approach & key points

Framework: null. (a) calculate: given > formula > substitution > result with units > interpretation | (b) explain: definition/context > points in order > small example > short close | (c) calculate: given > formula > substitution > result with units > interpretation Full marks: Accurate calculations with clear steps, correct application of codes, and well-structured explanations.

  • Cost ₹5,30,000, life 20 years, scrap ₹1,50,000
  • D = ₹19,000 a year (3.585%); fund at 9.45 years ≈ ₹1,79,600
  • Book value after 12 years ₹3,02,000 plus ₹1,50,000 = ₹4,52,000
  • New D = ₹37,750 a year = 8.35%
  • Definition and effects of dampness
  • Causes: rising damp, rain penetration, condensation, leakage
  • Remedies: DPC, cavity wall, coatings, drainage
  • Treatment of existing buildings: injection DPC, electro-osmosis, grouting
  • Original design traffic 15.84 msa with A = 1815 CV/day, F = 15.937
  • Revised traffic A = 750 × 1.1⁷ = 1461.5 per direction
  • Equate 365 A·VDF·LDF·[(1.1)ⁿ − 1]/0.1 to 15.84 msa
  • n ≈ 11.45 years

B

Q5
50M Compulsory calculate Hydrology and water quality

(a) A 6-hour unit hydrograph has the following ordinates (time in hr : ordinate in m³/s): 0 : 0; 6 : 200; 12 : 550; 18 : 750; 24 : 650; 30 : 550; 36 : 400; 42 : 270; 48 : 150; 54 : 50; 60 : 0. If φ index is 0.3 cm/hr and base flow is 25 m³/s, determine the ordinates of resulting hydrograph of flow in the catchment due to the storm given below (time from start of storm in hr : accumulated rainfall in cm): 0 : 0; 6 : 3; 12 : 8; 18 : 12. (10 marks) (b) The annual precipitation and evaporation from each of the sub-areas P, Q, R and S are given below for a catchment (sub-area : area in km², annual precipitation in mm, annual evaporation in mm): P : 15, 1000, 500; Q : 5, 800, 400; R : 10, 900, 440; S : 18, 1200, 650. Calculate the following for catchment : (i) Annual average precipitation (ii) Annual average evaporation (iii) Annual runoff coefficients for the sub-areas and for the total catchment taken as a whole assuming no change in the ground water storage on an annual basis. (10 marks) (c) Route the above flood hydrograph through a river reach (time in hr : inflow in m³/s): 0 : 10; 4 : 20; 8 : 30; 12 : 30; 16 : 25; 20 : 20; 24 : 35; 28 : 12. The value of x and K in the Muskingham equation have been identified as 0.25 and 8 hr. The initial outflow discharge from the reach is 10 m³/s. (10 marks) (d) Explain the significance of the following from the point of view of water quality criteria : (i) Nitrites (ii) Nitrates (iii) E-coli (iv) B.O.D. (v) Dissolved oxygen (10 marks) (e) In a continuous flow settling tank 4 m deep and 80 m long, calculate the flow velocity for effective removal of 0.03 mm particles at 25°C. The specific gravity of the particles is 2.65 and kinematic viscosity (v) for water may be taken as 0.01 cm²/sec. (10 marks)

हिंदी में पढ़ें

(क) एक 6-घंटा एकांक जललेख की निम्नलिखित कोटियाँ हैं (समय घंटा : कोटि m³/s): 0 : 0; 6 : 200; 12 : 550; 18 : 750; 24 : 650; 30 : 550; 36 : 400; 42 : 270; 48 : 150; 54 : 50; 60 : 0 । यदि φ सूचकांक 0.3 cm/hr एवं आधार प्रवाह 25 m³/s है, तो नीचे दिए गए वृष्टि (वृष्टि के आरंभ से समय घंटा : संचित वर्षा cm: 0 : 0; 6 : 3; 12 : 8; 18 : 12) के कारण अपवाह क्षेत्र में उत्पन्न होने वाले प्रवाह के जललेख की कोटियों को निर्धारित कीजिए । (10 अंक) (ख) एक अपवाह क्षेत्र के सभी उपक्षेत्रों P, Q, R एवं S के वार्षिक वृष्टिपात और वाष्पीकरण नीचे दिए गए हैं (उपक्षेत्र : क्षेत्रफल km², वार्षिक वृष्टिपात mm, वार्षिक वाष्पीकरण mm): P : 15, 1000, 500; Q : 5, 800, 400; R : 10, 900, 440; S : 18, 1200, 650 । अपवाह क्षेत्र के लिए निम्नलिखित की गणना कीजिए : (i) वार्षिक औसत वृष्टिपात (ii) वार्षिक औसत वाष्पीकरण (iii) वार्षिक अपवाह गुणांक, सभी उपक्षेत्रों के लिए और संपूर्ण सकल अपवाह क्षेत्र के लिए यह मानते हुए कि वार्षिक आधार पर भौम जल संचयन में कोई परिवर्तन नहीं है । (10 अंक) (ग) नदी के एक खंड के लिए निम्नलिखित बाढ़ जलालेख का मार्गाभिगमन कीजिए (समय घंटा : अंतर्वाह m³/s): 0 : 10; 4 : 20; 8 : 30; 12 : 30; 16 : 25; 20 : 20; 24 : 35; 28 : 12 । मस्किंघम समीकरण में प्रयुक्त होने वाले x एवं K का मान 0.25 एवं 8 घंटे हैं । नदी खंड से होने वाला प्रारम्भिक बहिर्प्रवाह निस्सरण 10 m³/s है । (10 अंक) (घ) जल की गुणवत्ता की कसौटी की दृष्टि से निम्नलिखित की सार्थकता की व्याख्या कीजिए : (i) नाइट्राइट (ii) नाइट्रेट (iii) ई-कोलाई (iv) बी.ओ.डी. (v) घुलित ऑक्सीजन (10 अंक) (ङ) एक निरंतर प्रवाह अवसाद टंकी जो कि 80 m लम्बी एवं 4 m गहरी है, उसमें 25°C पर 0.03 mm के कणों को प्रभावी रूप से हटाने के लिए प्रवाह गति ज्ञात कीजिए । कणों का विशिष्ट घनत्व 2.65 है और जल की शुद्धगतिक श्यानता (v) को 0.01 cm²/sec लिया जा सकता है । (10 अंक)

Answer approach & key points

(a) calculate: given > formula > substitution > result with units > interpretation | (b) calculate: given > formula > substitution > result with units > interpretation | (c) calculate: given > formula > substitution > result with units > interpretation | (d) explain: definition/context > points in order > small example > short close | (e) calculate: given > formula > substitution > result with units > interpretation Full marks: All parts solved with correct methods, clear steps, and proper units.

  • Incremental rainfall 3, 5 and 4 cm; φ loss 1.8 cm per 6 h
  • Effective rainfall 1.2, 3.2 and 2.2 cm
  • DRH = 1.2U(t) + 3.2U(t − 6) + 2.2U(t − 12)
  • Add base flow 25 m³/s; peak 4415 m³/s
  • Area-weighted P = 1033.3 mm
  • Area-weighted E = 533.3 mm
  • Runoff = P − E: 500, 400, 460 and 550 mm for the sub-areas
  • Runoff coefficients 0.50, 0.50, 0.51, 0.46; catchment 0.48
  • Δt = 4 h, C₀ = 0, C₁ = 0.5, C₂ = 0.5
  • O(t + Δt) = C₀I₂ + C₁I₁ + C₂O₁
  • Outflows 10, 10, 15, 22.5, 26.25, 25.63, 22.81, 28.91
  • Attenuation and lag of the outflow peak
  • Nitrite: recent pollution and toxicity
  • Nitrate: end product; eutrophication and blue-baby syndrome
  • E. coli: faecal contamination indicator
  • BOD and DO: organic load and aquatic life support
  • Stokes' law v_s = g(G − 1)d²/(18ν) = 0.081 cm/s
  • Check Re < 1
  • v_s/v = H/L
  • v = 0.081 × 80/4 = 1.62 cm/s
Q6
50M solve Groundwater hydrology and water supply

(a) (i) A 50 cm well in an unconfined aquifer of saturated thickness 45 m yields 600 lpm under a drawdown of 3 m at the pumping well. What will be the discharge under a drawdown of 6 m ? Consider the radius of influence as 500 m. (ii) What will be the discharge in a 30 cm well under a drawdown of 3 m for the unconfined aquifer as mentioned in part (i). (20 marks) (b) How does the peak hour demand affect the design of a water supply scheme ? Sketch the fluctuation in demand for typical Indian conditions. (15 marks) (c) (i) The B.O.D. of a sewage incubated for one day at 25°C has been found to be 100 mg/l. What will be the 5 day, 20°C B.O.D. ? Assume K₂₀ = 0·12 at 20°C. Take temperature coefficient, φ = 1·056. (ii) Despite widespread use of B.O.D., it has some limitations. Mention all those limitations. (15 marks)

हिंदी में पढ़ें

(a) (i) 45 m की संतृप्त मोटाई के एक अपरिरुद्ध जलभृत में 50 cm का एक कुआँ, एक पम्पिंग कुएँ में 3 m अपकर्ष (ड्रॉडाउन) पर 600 lpm का उत्सर्जन देता है । 6 m अपकर्ष पर इसका निस्सरण क्या होगा ? प्रभाव त्रिज्या को 500 m मान लीजिए । (ii) भाग (i) में उल्लिखित अपरिरुद्ध जलभृत के लिए 3 m अपकर्ष पर 30 cm के कुएँ का निस्सरण क्या होगा ? (20) (b) चरम घंटा माँग एक जलप्रदाय परियोजना को कैसे प्रभावित करती है ? विशिष्ट भारतीय परिस्थितियों के लिए माँग के उच्चावचन को आरेखित कीजिए । (15) (c) (i) 25°C पर एक दिन के लिए उद्भवन किए गए एक अपशिष्ट का बी.ओ.डी. 100 mg/l पाया गया । अपशिष्ट के 20°C पर पाँच दिन के बी.ओ.डी. का मान क्या होगा ? 20°C पर K₂₀ = 0·12 मान लीजिए । तापमान गुणांक, φ = 1·056 लीजिए । (ii) बी.ओ.डी. के व्यापक उपयोग के बावजूद इसकी कुछ सीमाएँ हैं । इन सभी सीमाओं का उल्लेख कीजिए । (15)

Answer approach & key points

Framework: null. (a) calculate: given > formula > substitution > result with units > interpretation | (b) explain: definition/context > points in order > small example > short close | (c) calculate: given > formula > substitution > result with units > interpretation Full marks: Correct application of Dupuit-Thiem and BOD formulas with clear steps; well-labelled sketches; comprehensive list of limitations.

  • Dupuit–Thiem Q = πK(H² − h_w²)/ln(R/r_w)
  • Ratio (45² − 39²)/(45² − 42²) = 504/261, so Q = 1159 lpm
  • K ≈ 8.0 m/day from the first well
  • 30 cm well: Q = 600 ln2000/ln3333 ≈ 562 lpm
  • Peak hour ≈ 1.5 × maximum daily ≈ 2.7 × average
  • Distribution mains, pumps and pressure sized for peak flow
  • Service reservoir balancing storage; treatment for maximum daily demand
  • Sketch: night minimum, morning and evening peaks
  • K₂₅ = 0.12 × 1.056⁵ = 0.1576 per day
  • L = 100/(1 − 10^(−0.1576)) = 328.6 mg/L
  • BOD₅ at 20°C = 246 mg/L
  • Limitations: only biodegradable matter, slow test, nitrification and toxicity interference
Q7
50M discuss Environmental and Water Resources Engineering

(a) Discuss the following operational difficulties encountered in the operation of Activated Sludge process : (i) Rising Sludge or Floating Sludge (ii) Sludge Bulking What kind of impact these are having in the operation of Activated Sludge process ? (20 marks) (b) Explain the following : (i) Specific capacity of a well (ii) Specific yield of an aquifer (iii) Perched water table (iv) Intrinsic permeability (v) Bulk pore velocity (15 marks) (c) (i) Define Delta, Duty and Base Period, and derive the relationship among them. (7 marks) (ii) Discuss the factors influencing the selection of site for a proposed dam. (8 marks)

हिंदी में पढ़ें

(a) सक्रिय अवपंक प्रक्रिया के संचालन में आने वाली निम्नलिखित कठिनाइयों की चर्चा कीजिए : (i) आरोही अवपंक या प्लवी अवपंक (ii) अवपंक का फूलना सक्रिय अवपंक प्रक्रिया के संचालन में इनका किस प्रकार का प्रभाव होता है ? (20 अंक) (b) निम्नलिखित की व्याख्या कीजिए : (i) कुएँ की विशिष्ट क्षमता (ii) जलभृत का विशिष्ट उत्सर्जन (iii) अध्यासीन भौम जल स्तर (iv) नैज पारगम्यता (v) पुंज छिद्र गति (15 अंक) (c) (i) कृति (ड्यूटी), डेल्टा और आधार काल को परिभाषित कीजिए और उनके बीच के सम्बन्ध को व्युत्पन्न कीजिए । (7 अंक) (ii) एक प्रस्तावित बांध के स्थान के चुनाव को प्रभावित करने वाले कारकों की चर्चा कीजिए । (8 अंक)

Answer approach & key points

Framework: null. (a) discuss: intro > 3-4 dimensions > example > balanced close | (b) explain: definition/context > points in order > small example > short close | (c(i)) derive: given > assumptions > stepwise derivation > result > check | (c(ii)) discuss: intro > 3-4 dimensions > example > balanced close Full marks: Comprehensive definitions, correct derivations, and detailed discussion of impacts and factors.

  • Rising sludge is caused by denitrification in the clarifier and gas bubbles
  • Bulking is caused by filamentous organisms and gives a high SVI (> 150 mL/g)
  • Causes: low DO, F/M, nutrients, sludge age
  • Impact on effluent quality and remedies such as wasting, DO control and selectors
  • Specific capacity = Q/s
  • Specific yield: gravity-drained volume per unit volume
  • Perched water table above a low-permeability lens
  • Intrinsic permeability k (m²) and seepage velocity v_s = Ki/n
  • Definitions of B, D and Δ
  • Volume 86 400 B m³ for 1 cumec over B days
  • D hectares = 10⁴ D m²
  • Δ = 8.64 B/D metres
  • Narrow gorge with wide storage valley
  • Sound foundation and watertight reservoir
  • Adequate catchment inflow with low silt
  • Submergence, rehabilitation, seismicity, cost and environment
Q8
50M design Irrigation, Environmental and Air Pollution Engineering

(a) (i) Design a trapezoidal concrete lined channel to carry a discharge of 300 m³/s at a slope of 1 in 4000. The side slope of the channel may be taken as 1·5 : 1. The value of n for the lining material may be taken as 0·0125. Assume the B/D ratio as 5. (10 marks) (ii) Describe briefly different type of spillways used in dams and methods used for dissipating energy of water discharged from them. (10 marks) (b) Mention the sources and health effects on human being of the following elements with reference to Air pollution : Lead, Cadmium, Nickel, Mercury, Carbon Monoxide (15 marks) (c) (i) Discuss the factors that must be considered in evaluating potential sanitary landfill sites. (ii) How does the occurrence of gases and leachate in sanitary landfill take place ? Explain with the help of chemical reactions taking place. (15 marks)

हिंदी में पढ़ें

(a) (i) 4000 में 1 की प्रवणता पर 300 m³/s का निस्सरण ले जाने वाली एक समलम्बाकार कंक्रीट आस्तरित वाहिका का अभिकल्पन कीजिए । वाहिका की पार्श्व प्रवणता को 1·5 : 1 लिया जा सकता है । अस्तर सामग्री के लिए n का मान 0·0125 लिया जा सकता है । B/D अनुपात को 5 मान लीजिए । (10 अंक) (ii) बांधों में उपयोग किए जाने वाले विभिन्न प्रकार के उत्लव मार्गों और उनसे निस्सरित जल की ऊर्जा के क्षय के लिए उपयोग की जाने वाली विधियों का वर्णन संक्षेप में कीजिए । (10 अंक) (b) वायु प्रदूषण के संदर्भ में निम्नलिखित तत्त्वों के स्रोतों और मनुष्य के स्वास्थ्य पर इनके प्रभावों का उल्लेख कीजिए : सीसा (लैड), कैडमियम, निकेल, पारा (मर्करी), कार्बन मोनोक्साइड (15 अंक) (c) (i) उन कारकों की चर्चा कीजिए जिन पर संभाव्य स्वच्छ भू-भराव स्थलों के मूल्यांकन में आवश्यक रूप से विचार किया जाना चाहिए । (ii) स्वच्छ भू-भराव में गैसों और निषालक (लीचेट) की उत्पत्ति कैसे होती है ? इसमें होने वाली रासायनिक प्रतिक्रियाओं की सहायता से व्याख्या कीजिए । (15 अंक)

Answer approach & key points

(a(i)) calculate: given > formula > substitution > result with units > interpretation | (a(ii)) describe: define > structure or process in order > labelled diagram > significance | (b) highlight: name the salient points > one line of substance each > close | (c) discuss: intro > 3-4 dimensions > example > balanced close Full marks: Complete design with checks; comprehensive spillway description; detailed pollutant analysis; clear chemical mechanisms for landfill.

  • A = 6.5D², P = 8.606D, R = 0.755D
  • Manning gives 6.82 D^(8/3) = 300
  • D = 4.13 m and B = 20.67 m
  • Check V = 2.70 m/s, Fr = 0.47, freeboard 0.75 m
  • Ogee, chute, side-channel, shaft, siphon and labyrinth or stepped spillways
  • Features and suitable use of each
  • Stilling basin with chute and baffle blocks, end sill
  • Roller and ski-jump buckets, plunge pool
  • Lead: petrol, batteries; nervous system and kidney
  • Cadmium: batteries, electroplating; kidney and bone damage
  • Nickel and mercury sources and effects
  • Carbon monoxide: incomplete combustion; carboxyhaemoglobin
  • Site factors: capacity, geology, groundwater, distance and access
  • Leachate from percolation through waste
  • Hydrolysis, acid formation and methanogenesis reactions
  • Landfill gas composition and hazards

Practice Civil Engineering 2023 Paper II answer writing

Pick any question above, write your answer, and get a detailed AI evaluation against UPSC's standard rubric.

Start free evaluation →

Write this answer and get it marked in about 20 seconds

Free account: 5 AI evaluations a month, marked against the rubric above.

Start free

Already have an account? Log in