Civil Engineering 2024 Paper II 50 marks Solve

Q4

(a) The network of a certain project is shown in the figure given below with the estimated time duration (in days) of various activities. Determine the following : (i) Earliest event time (ii) Latest event time (iii) Earliest start and finish time of each activity (iv) Latest start and finish time of each activity (v) Total float of each activity (vi) Critical path of the network (Assume the scheduled completion time of the project equal to the earliest event time of the last event) 20 (b) Prepare a detailed analysis of rate (₹ per sq. m) for a 25 mm thick cement concrete (1 : 2 : 4) floor with cement finishing coat. 15 (c) Sketch a typical diamond crossing and label all its components. Design a diamond crossing between two B.G. tracks crossing each other at an angle of 1 in 8·5. 15

हिंदी में प्रश्न पढ़ें

(a) नीचे दिए गए चित्र में एक निश्चित परियोजना का जाल (नेटवर्क) विभिन्न क्रियाओं की आकलित समयावधि (दिनों में) के साथ दर्शाया गया है। निम्नलिखित को ज्ञात कीजिए : (i) यथाशीघ्र घटना काल (ii) यथाविलम्बित घटना काल (iii) प्रत्येक क्रिया का यथाशीघ्र प्रवर्तन काल एवं यथाशीघ्र समाप्ति काल (iv) प्रत्येक क्रिया का यथाविलम्बित प्रवर्तन काल एवं यथाविलम्बित समाप्ति काल (v) प्रत्येक क्रिया का कुल प्लव (फ्लोट) (vi) जाल का क्रांतिक पथ (परियोजना का निर्धारित समाप्ति काल अंतिम घटना के यथाशीघ्र घटना काल के बराबर मान लीजिए) 20 (b) सीमेंट के आखिरी लेप के साथ बनाए गए एक 25 मिमी मोटे सीमेंट कंक्रीट (1 : 2 : 4) फर्श के लिए विस्तृत विश्लेषण दर (₹ प्रति वर्ग मीटर) तैयार कीजिए। 15 (c) एक प्राकृतिक समचतुर्भुज (डायमंड) क्रॉसिंग का चित्र बनाइए और उसके सभी घटकों को नामांकित कीजिए। यदि दो बड़ी लाइन (बी.जी.) रेलपथ एक-दूसरे को 8·5 में 1 के कोण पर क्रॉस करते हैं, तो उनके बीच एक समचतुर्भुज (डायमंड) क्रॉसिंग का अभिकल्पन कीजिए। 15

Directive word: Solve

This question asks you to solve. The directive word signals the depth of analysis expected, the structure of your answer, and the weight of evidence you must bring.

See our UPSC directive words guide for a full breakdown of how to respond to each command word.

How this answer will be evaluated

Approach

Solve this multi-part technical problem by allocating approximately 40% time to part (a) CPM network analysis, 30% to part (b) rate analysis, and 30% to part (c) diamond crossing design. Begin with forward and backward pass calculations for the network, followed by systematic rate analysis using current DSR/CPWD norms, and conclude with geometric design calculations and neat sketching for the railway crossing.

Key points expected

  • Part (a): Correct computation of EET and LET for all events using forward and backward pass method; identification of critical path with zero total float
  • Part (a): Accurate calculation of EST, EFT, LST, LFT and total float for each activity with proper tabulation
  • Part (b): Detailed rate analysis showing material quantities (cement, sand, aggregate), labour components, and cost breakdown per sq.m for 25mm thick CC 1:2:4 floor with finishing
  • Part (b): Inclusion of wastage, water charges, overhead charges, and contractor profit as per standard practice; reference to CPWD/State PWD schedule of rates
  • Part (c): Correct geometric design of diamond crossing for BG track with 1 in 8.5 crossing angle: calculation of nose of crossing, throat length, and check rails
  • Part (c): Neat sketch showing all components: four noses, two obtuse angle crossings, two acute angle crossings, check rails, wing rails, and sleeper layout
  • Part (c): Application of relevant formulae: sin α = 1/8.5, calculation of theoretical and actual nose of crossing, flaring of check rails

Evaluation rubric

DimensionWeightMax marksExcellentAveragePoor
Concept correctness20%10Demonstrates flawless understanding of CPM methodology (forward/backward pass, float concepts), rate analysis components, and diamond crossing geometry including all design formulae for 1 in 8.5 crossing angleShows basic understanding of CPM calculations and rate analysis but makes minor errors in diamond crossing geometry or omits some components in rate breakdownConfuses EET/LET concepts, misses critical activities, or applies wrong formulae for crossing angle; rate analysis lacks essential components
Numerical accuracy20%10All calculations precise: EET/LET correct to the day, rate analysis sums accurately with proper unit costs, diamond crossing dimensions (nose, throat, check rail flaring) computed correctly using sin α = 1/8.5Minor arithmetic errors in some calculations (1-2 days off in network, 5-10% error in quantities, small dimensional errors) but method is soundMajor calculation errors, wrong use of formulae, or completely incorrect numerical values; failure to compute sin α or apply crossing angle correctly
Diagram quality20%10Clear, scaled network diagram with activity durations labeled; neat diamond crossing sketch showing all four noses, check rails, wing rails, sleeper layout, and crossing angle; proper labeling of all componentsDiagrams present but poorly scaled or with missing labels; network diagram lacks clarity in event numbering; diamond crossing sketch incompleteMissing diagrams, illegible sketches, or failure to provide network/diamond crossing drawings as explicitly demanded
Step-by-step derivation20%10Systematic presentation: tabular EET/LET computation with clear pass identification, detailed rate analysis with quantity calculations per unit, stepwise geometric derivation of crossing dimensions with formulae statedSome steps shown but lacks systematic tabulation; rate analysis condensed; geometric derivation skips intermediate stepsNo working shown, jumps to final answers, or presents only final results without methodology; illegible or disorganized presentation
Practical interpretation20%10Relates critical path to project crashing decisions, justifies rate analysis assumptions with reference to CPWD/State PWD DSR 2022-23, explains practical significance of check rails and flaring in diamond crossing for Indian Railways BG standardsBrief mention of practical relevance without specific standards reference; generic statements about project management or constructionNo practical context provided; purely theoretical treatment without connection to actual construction practice or railway engineering standards

Practice this exact question

Write your answer, then get a detailed evaluation from our AI trained on UPSC's answer-writing standards. Free first evaluation — no signup needed to start.

Evaluate my answer →

More from Civil Engineering 2024 Paper II