Q1 50M Compulsory solve Probability, sampling, quality control, maintenance decision, e-governance
(a) A train is scheduled to arrive at a station at a random time between 09:00 AM and 09:30 AM. The actual arrival time is equally likely to be any moment within this interval.
(i) Define a suitable probability density function (PDF).
(ii) What is the probability that the train will arrive before 09:13 AM ?
(iii) Find the expected arrival time and the variance of the arrival time.
(iv) Given that the train has not arrived by 09:11 AM, what is the expected arrival time ?
10
(b) Determine the required sample size for estimating the true weight cereal container from a population of N = 5000.
Based on the past records variance of weight is 121 grams and this estimate should be within 2·5 grams of the true average weight with 99% confidence.
Will there be a change in the size of the sample if we assume population to be infinite ? If so, explain by how much ? (Table enclosed)
10
(c) A manufacturing facility specializing in Sheet Metal Production has implemented a Statistical Quality Control Program to monitor and improve process performance. As a part of this initiative, an Engineer has recorded the number of visible surface defects identified on 20 sequential metal sheets, each representing one production unit. The data collected during this inspection phase are given below :
[Table with Sheet No. 1-20 and Defect Counts: 5, 6, 4, 4, 6, 7, 0, 6, 5, 3, 1, 4, 5, 3, 6, 4, 3, 1, 3, 4]
Using the above information :
(i) Determine the Center line (CL), Upper control limit (UCL) and Lower control limit (LCL).
(ii) Plot the appropriate Control Chart and interpret the result.
10
(d) A Tech Solutions is a mid-sized IT consulting company specializing in automated HR and payroll systems for small business. The company has successfully digitized most of its operations, relying heavily on its internal computer systems for payroll processing and report generations. However, despite its automation efforts, the computer system has experienced periodic failures. Over the past 20 months, the computer system has broken down as indicated in the table below :
Each breakdown results in an average loss of ₹4500/- due to time delay and technical service expenses. As a preventive measure, company is considering a monthly service contract for preventive maintenance. If they sign up for the contract, the average number of breakdowns is expected to decrease to 1 per month, and the contract would cost ₹3300/- per month.
Based on the given information, advise that the company should go for contract for preventive maintenance or not ?
10
(e) Critically analyse the advantages of E Governance for Government, Public and Business giving suitable examples.
10
हिंदी में पढ़ें
(a) एक ट्रेन 09:00 AM से 09:30 AM के बीच यादृच्छिक समय पर एक स्टेशन पर आने वाली है । वास्तविक आगमन समय इस अंतराल के भीतर किसी भी क्षण होने की समान संभावना है ।
(i) उचित संभाव्यता घनत्व फलन (पीडीएफ) परिभाषित कीजिए ।
(ii) 09:13 AM के पहले ट्रेन के आने की क्या संभावना है ?
(iii) अपेक्षित आगमन समय और आगमन समय का अंतर बताइए ।
(iv) यह देखते हुए कि ट्रेन 09:11 AM तक नहीं आई है, अपेक्षित आगमन का समय क्या है ?
10
(b) N = 5000 आबादी में से अनाज के कंटेनर का सटीक वजन जानने के लिए आवश्यक नमूना आकार निर्धारित कीजिए ।
पिछले रिकॉर्ड पर आधारित वजन का परिवर्तन 121 ग्राम है । यह आकलन सही औसत वजन के 2·5 ग्राम के अंदर 99% भरोसे के साथ होना चाहिए ।
अगर हम अनंत आबादी मान लें, तो क्या नमूने के आकार में परिवर्तन होगा ? अगर हाँ, तो कितना होगा, समझाइए । (सारणी संलग्न है)
10
(c) शीट मेटल उत्पादन में विशेषता वाली विनिर्माण सुविधा ने प्रक्रिया प्रदर्शन को अनुश्रवण एवं सुधार के लिए सांख्यिकी गुण नियंत्रण कार्यक्रम अमल किया है। इस पहल के एक हिस्से के रूप में एक अभियंता ने, 20 अनुक्रमिक धातु शीट जो कि प्रत्येक एक उत्पादन इकाई का प्रतिनिधित्व करता है, दृश्यमान सतह दोषों की संख्या दर्ज की है। निरीक्षण के दौरान एकत्र किए गए आँकड़े नीचे दिए गए हैं :
[Table with Sheet No. 1-20 and Defect Counts: 5, 6, 4, 4, 6, 7, 0, 6, 5, 3, 1, 4, 5, 3, 6, 4, 3, 1, 3, 4]
उपर्युक्त जानकारी का उपयोग करते हुए :
(i) केन्द्र रेखा (सीएल), ऊपरी नियंत्रण सीमा (यूसीएल) और निचली नियंत्रण सीमा (एलसीएल) का निर्धारण कीजिए।
(ii) उपयुक्त नियंत्रण चार्ट अंकित कीजिए और परिणाम की व्याख्या कीजिए।
10
(d) A Tech Solutions एक मध्यम आकार की आई टी परामर्श फर्म है जो लघु व्यापार के लिए मानव संसाधन एवं वेतन प्रणालियों में विशेषज्ञता रखती है। कंपनी ने अपने परिचालन में अपने आंतरिक कंप्यूटर सिस्टम पर बहुत अधिक निर्भर करते हुए वेतन भुगतान की प्रक्रिया और रिपोर्ट बनाने का सफलता पूर्वक डिजिटलीकरण कर लिया है। तथापि इसके स्वचालन प्रयासों के बावजूद कंप्यूटर सिस्टम को समय-समय पर विफलताओं का अनुभव हुआ है। पिछले 20 महीनों में नीचे दिए तालिका में बताए गए आंकड़ों के अनुसार कंप्यूटर सिस्टम खराब हुआ है :
हर व्यवधान समय में देरी और तकनीकी खर्च के कारण औसतन ₹4500/- नुकसान होता है। कंपनी निवारक उपाय के रूप में निवारक रखरखाव के लिए मासिक सेवा अनुबंध पर विचार कर रही है। अगर कंपनी अनुबंध पर हस्ताक्षर करे तो व्यवधान की औसत संख्या एक हर महीने होने की उम्मीद है और अनुबंध का खर्च ₹3300/- हर महीने होगा।
दी गई जानकारी के आधार पर सलाह दीजिए कि कंपनी को इस निवारक रखरखाव के लिए अनुबंध करना चाहिए या नहीं ?
10
(e) सरकार, जनता और व्यापार में ई गवर्नेंस के लाभों का उपयुक्त उदाहरण देते हुए आलोचनात्मक विश्लेषण कीजिए ।
10
Answer approach & key points
Solve all five numerical and analytical parts systematically, allocating approximately 20% time to each sub-part given equal 10-mark weighting. Begin with precise mathematical derivations for (a) continuous uniform distribution and conditional expectation, (b) finite population correction for sample size, (c) c-chart construction with control limit calculations, (d) expected cost comparison for maintenance decisions, and conclude with (e) critical analysis of e-governance stakeholders. Present calculations step-wise with proper formulae, units, and interpretations.
- (a) Define PDF f(t) = 1/30 for t ∈ [0,30] minutes; calculate P(T<13) = 13/30; derive E(T)=15 min, Var(T)=75; apply memoryless property for conditional expectation E(T|T>11) = 11 + 15 = 26 min or 09:26 AM
- (b) Apply sample size formula n₀ = Z²σ²/E² with Z=2.576, σ²=121, E=2.5; compute n₀ ≈ 139; apply finite population correction n = n₀/(1+n₀/N) ≈ 135; show infinite population increases sample size by ~4 units
- (c) Calculate c̄ = Σcᵢ/k = 80/20 = 4; determine CL=4, UCL=4+3√4=10, LCL=max(0,4-3√4)=0; construct c-chart and interpret no points outside limits, process in statistical control
- (d) Compute expected breakdown cost without contract: compare historical rate (20 breakdowns/20 months = 1/month) vs stated data; calculate expected monthly cost = ₹4500 vs contract cost ₹3300 + ₹4500×1 = ₹7800; recommend against contract if current rate ≤ 1, or detailed cost-benefit if data shows higher breakdowns
- (e) Critically analyse e-governance advantages: Government (efficiency, transparency—MCA21, GSTN), Public (accessibility, grievance redressal—UMANG, Digital India), Business (ease of doing business, reduced corruption—e-way bills, GeM); include challenges like digital divide, cybersecurity
Q2 50M solve Trend analysis, hypothesis testing, linear programming
(a) The electrical power demand of TATA Power Corporation from 2018 to 2024, measured in megawatts, is provided below. Using the data, forecast the demand for the year 2025 by fitting and plotting the linear trend line.
Year | Electrical Power Demand (Megawatts)
2018 | 94
2019 | 99
2020 | 100
2021 | 110
2022 | 125
2023 | 162
2024 | 142
15
(b) In a study to evaluate the effectiveness of two different animal feeds, researchers recorded the weight gains (in kilograms) of animals after fed each type of feed.
Feed A | 45 | 48 | 47 | 50 | 46 | 49 | 47 | 48
Feed B | 51 | 53 | 52 | 55 | 50 | 52 | 54 | 33
(i) If the two samples are considered independent, can we conclude that Feed B is more effective than Feed A at the 0·025 level of significance ?
(ii) Also examine the case if the same set of eight animals received both feeds, and test at the 0·01 level of significance. (Table enclosed)
15
(c) Techline Pvt. Ltd. is a consumer electrics manufacturing concern producing three models of Smart Devices : X, Y and Z. The company operates under the constraints of two key resources, viz. raw materials and labor hours. Each week, the availability of raw materials is restricted to 800 kg, while labor availability is limited to 600 hours. To maximize profit, the company needs to decide, how many units of each product to manufacture weekly without exceeding the available resources. The relevant details for each product are provided below :
| Product | Raw Material per unit (Kg) | Labor Hours per unit (Hours) | Profit contribution per unit (₹) |
|---------|---------------------------|------------------------------|----------------------------------|
| X | 6 | 5 | 80 |
| Y | 4 | 4 | 60 |
| Z | 2 | 3 | 40 |
(i) Formulate this scenario as a Linear Programming Problem (LPP), and solve it for optimal product mix.
(ii) Based on the optimal solution, analyze the situation if the company wants to introduce a New product W, requiring 2 kg of raw materials and 2 hours of labor hours per unit. Its estimated profit contribution is ₹35/- per unit.
Should the company include this new product in its production mix ?
20
हिंदी में पढ़ें
(a) टाटा पावर कॉरपोरेशन के 2018-2024 तक मेगावाट में मापी गई विद्युत शक्ति की मांग नीचे दी गई है :
वर्ष | विद्युत शक्ति की मांग (Megawatts)
2018 | 94
2019 | 99
2020 | 100
2021 | 110
2022 | 125
2023 | 162
2024 | 142
इस डाटा का उपयोग करते हुए फिटिंग व प्लॉटिंग से रैखिक प्रवृत्ति रेखा द्वारा वर्ष 2025 के लिए मांग का पूर्वानुमान लगाइए ।
15
(b) शोधकर्ताओं ने पशु आहारों के दो प्रकार की प्रभावशीलता का मूल्यांकन करने के लिए एक अध्ययन में पशुओं की प्रत्येक प्रकार के चारे को खिलाने के बाद भार (किलोग्राम में) बढ़ने का रिकॉर्ड किया ।
चारा A | 45 | 48 | 47 | 50 | 46 | 49 | 47 | 48
चारा B | 51 | 53 | 52 | 55 | 50 | 52 | 54 | 33
(i) अगर हम दोनों नमूनों को स्वतंत्र मानते हैं तो क्या हम यह निष्कर्ष निकाल सकते हैं कि महत्व स्तर 0·025 पर चारा B चारा A से अधिक प्रभावी है ?
(ii) आठ जानवरों का वही समूह दोनों चारों को प्राप्त करते है तो 0·01 महत्व स्तर पर इस मामले की भी जाँच कीजिए । (सारणी संलग्न है)
15
(c) Techline Pvt. Ltd. एक इलेक्ट्रिक उपभोक्ता उत्पाद कर्ता है जो X, Y और Z तीन स्मार्ट उपकरण मॉडल बनाती है । कंपनी कच्चे माल व काम के घंटों, दो महत्वपूर्ण संसाधनों की बाधाओं के तहत कार्य करती है । प्रत्येक सप्ताह कच्चे माल की उपलब्धता 800 kg तक सीमित है जबकि श्रमिक उपलब्धता 600 hours तक सीमित है । लाभ को अधिकतम करने के लिए, उपलब्ध संसाधनों को पार किए बिना प्रत्येक उत्पाद की साप्ताहिक कितनी इकाइयाँ बनाती है, का निर्णय कंपनी को लेना है । प्रत्येक उत्पाद के प्रासंगिक विवरण नीचे दिए गए हैं ।
उत्पाद | प्रति यूनिट कच्चा माल (Kg) | प्रति यूनिट श्रम (घंटे) | प्रति यूनिट लाभ योगदान (रुपये)
X | 6 | 5 | 80
Y | 4 | 4 | 60
Z | 2 | 3 | 40
(i) रैखिक प्रोग्रामिंग समस्या (एल पी पी) द्वारा इष्टतम उत्पाद मिश्रण के लिए परिदृश्य तैयार कीजिए ।
(ii) अगर कंपनी एक नए उत्पाद W, जो प्रति यूनिट 2 kg कच्चा माल व दो श्रम घंटे चाहता है, को लाना चाहती है तो सर्वोत्तम संभव समाधान के आधार पर विश्लेषण कीजिए। इसका अनुमानित प्रति यूनिट मुनाफा ₹35/- है।
क्या कंपनी को इस नए उत्पाद को अपने उत्पादन मिश्रण में लाना चाहिए ?
20
Answer approach & key points
Solve this multi-part numerical question by allocating approximately 30% time to part (a) trend analysis with linear regression, 30% to part (b) hypothesis testing for both independent and paired samples, and 40% to part (c) linear programming formulation and sensitivity analysis. Begin with clear problem identification, show all computational steps with formulas, present results in structured tables, and conclude with managerial interpretations for each sub-part.
- Part (a): Calculate linear trend line using least squares method (Y = a + bX), compute 2025 forecast, and describe plotting procedure with proper axes labeling
- Part (b)(i): Conduct independent samples t-test with pooled variance, calculate t-statistic, compare with critical t-value at α=0.025 (one-tailed), and state conclusion about Feed B effectiveness
- Part (b)(ii): Perform paired t-test for same animals, compute mean difference and standard error, compare with critical t-value at α=0.01, and interpret results
- Part (c)(i): Formulate LPP with objective function (Max Z = 80X + 60Y + 40Z) and constraints (6X+4Y+2Z ≤ 800, 5X+4Y+3Z ≤ 600, X,Y,Z ≥ 0), solve using graphical or simplex method, identify optimal product mix and maximum profit
- Part (c)(ii): Calculate opportunity cost/range of feasibility for new product W, determine shadow prices, assess whether ₹35 profit covers resource opportunity cost, and give definitive recommendation
- For all parts: Show complete working with formulas, degrees of freedom, and critical values from enclosed table; interpret results in business context
Q3 50M calculate Operations management and PERT/CPM
3.(a) A company has an annual demand of 1600 units for an item, whose unit cost is ₹70/-. The annual holding cost comprises 18% for interest charges, 1% for insurance, 1·5% allowances for obsolescence of unit cost and ₹2·50 for building overheads, ₹3·40 for damage loss, and ₹7·0 miscellaneous costs. Placing each order costs the company ₹100/-.
(i) Calculate Economic Order Quantity (EOQ) and the total costs of stocking the units.
(ii) If the supplier of the items will only deliver batches of 250 units, how is the total variable cost influenced ?
(iii) If the supplier relaxes their order size requirements, as the company has limited storage space it can stock a maximum of 100 units at any time. What would be the optimal ordering policy and associated costs ? 15
(b) Consider the following aggregate planning problem for four months :
| | Regular time | Overtime | Subcontracting |
|---|---|---|---|
| Production capacity/month | 900 units | 300 units | 200 units |
| Production cost/unit | ₹6/- | ₹8/- | ₹9/- |
The forecasted demand for the next four months is 1300, 1400, 1225 and 1475 units respectively. Shortages are not permitted. The initial inventory is 50 units, and the carrying cost is ₹1·60 per unit per month.
Provide the aggregate plan for this problem. 15
(c) The warehouse owner of Quick Industries is considering a new computer system for accounting and inventory control. A computer vendor sent the following information about the system installation :
| Activity Identification | Activity description | Immediate Predecessor | Time (Days) Most optimistic | Time (Days) Most likely | Time (Days) Most pessimistic |
|---|---|---|---|---|---|
| A | Selection of Computer Model | – | 5 | 7 | 9 |
| B | Input/output System Design | A | 6 | 8 | 16 |
| C | Monitoring System Design | A | 5 | 9 | 13 |
| D | Computer Hardware Assembly | B | 16 | 21 | 26 |
| E | Development of main Programs | B | 11 | 19 | 27 |
| F | Input/output routines development | C | 9 | 10 | 17 |
| G | Database Creation | E | 5 | 9 | 13 |
| H | Installation of the system | D, F | 2 | 3 | 4 |
| I | Testing and Implementation | G, H | 7 | 8 | 9 |
(i) Draw the network diagram for this information. Identify the Critical Path and expected project completion time.
(ii) Calculate the probability that the project will be completed in 61 days.
(iii) When the company wants to be 95% sure that the system will be installed by a certain date, how many days prior to that should it start the work ? 20
हिंदी में पढ़ें
3.(a) एक कंपनी में किसी वस्तु की वार्षिक मांग 1600 इकाई है जिसकी लागत प्रति इकाई ₹70/- है। वार्षिक होल्डिंग लागत ब्याज शुल्क के रूप में 18%, बीमा के लिए 1%, इकाई लागत के अपचलन के लिए 1.5% भत्ता, भवन उपरिव्यय ₹2.50, क्षति हानि के लिए ₹3.40 और विविध लागत ₹7.0 है। प्रत्येक आर्डर देने में कंपनी को ₹100/- का खर्च आता है।
(i) आर्थिक आदेश मात्रा (ई ओ क्यू) की गणना कीजिए और स्टॉकिंग इकाइयों की कुल लागत गणना कीजिए।
(ii) यदि वस्तुओं का आपूर्तिकर्ता 250 इकाइयों के बैच (बैच) में ही वितरण करता है तो कुल परिवर्तनीय लागत कैसे प्रभावित होगा ?
(iii) चूंकि कंपनी के पास सीमित संग्रहण स्थान है, आपूर्तिकर्ता अपने आदेश आकार के आवश्यकताओं में ढील देने को तैयार है। अगर 100 इकाई ही किसी समय भंडार किया जा सकता है तो इष्टतम आदेश (आर्डरिंग) नीति क्या होगी और संबंधित लागत क्या होगी ? 9
(b) निम्नलिखित समग्र नियोजन समस्या को चार महीनों के लिए विचार कीजिए :
| | नियमित समय | अधिक समय तक | उपपठा करना |
|---|---|---|---|
| उत्पादन क्षमता/माह | 900 units | 300 units | 200 units |
| उत्पादन लागत/इकाई | ₹6/- | ₹8/- | ₹9/- |
अगले चार महीनों के लिए मांग पूर्वानुमान क्रमशः: 1300, 1400, 1225 और 1475 इकाई है । किसी भी चीज की कमी की अनुमति नहीं है । आरंभिक माल 50 इकाई है और वहन करने की लागत ₹1·60 प्रति इकाई प्रति माह है ।
इस समस्या हेतु समग्र योजना उपलब्ध कराइए । 15
(c) Quick Industries के गोदाम मालिक मालसूची नियंत्रण और लेखांकन के लिए एक नए कम्प्यूटर सिस्टम पर विचार कर रहा है। एक कम्प्यूटर विक्रेता ने सिस्टम स्थापित करने के लिए निम्नलिखित जानकारी दी है :
(i) इस जानकारी से जाल तंत्र (नेटवर्क) आरेख खींचिए। महत्वपूर्ण पथ की पहचान कीजिए और अपेक्षित परियोजना पूर्ण होने का समय बतलाइए।
(ii) 61 दिनों में इस परियोजना के पूरे होने की संभावना की गणना कीजिए।
(iii) जब कम्पनी 95% निश्चित करना चाहती है कि सिस्टम एक नियत तिथि तक स्थापित कर दिया जाए, ज्ञात कीजिए कि उसे कितने दिन पूर्व, कार्य को प्रारम्भ करना चाहिए। 11
Answer approach & key points
This numerical question demands precise calculations across five sub-parts: allocate ~30% time to 3(a) EOQ with holding cost breakdown (15 marks), ~25% to 3(b) aggregate planning with transportation method (15 marks), and ~45% to 3(c) PERT network with probability analysis (20 marks). Structure as: clear formula statement → step-wise computation → final answer with units → brief interpretation where asked.
- 3(a)(i): Correct EOQ formula application with total holding cost = 18%+1%+1.5% of ₹70 + ₹2.50+₹3.40+₹7.0 = ₹12.60+₹12.90 = ₹25.50/unit/year; EOQ = √(2×1600×100/25.50) ≈ 112 units; total cost calculation
- 3(a)(ii): Total variable cost at Q=250 vs EOQ, showing cost penalty for batch constraint; compare ordering + holding costs
- 3(a)(iii): Modified EOQ under storage constraint (max 100 units); optimal policy becomes ordering at capacity limit with adjusted cost analysis
- 3(b): Transportation method/linear programming formulation for aggregate planning; month-wise production allocation across regular, overtime, subcontracting minimizing total cost (production + inventory carrying); show inventory balance constraints
- 3(c): PERT network construction with AOA or AON; ES/EF/LS/LF calculations; critical path identification; variance and Z-score for probability; 95% confidence time calculation using normal distribution
Q4 50M discuss Information systems and expert systems
4.(a) (i) "Expert Systems play a significant role in Organisations." Discuss it giving at least four benefits of Expert Systems. 10
(ii) Elaborate the different components of Expert Systems giving suitable examples. 10
(b) (i) "Information Resource Management is a strategic plan of an organisation." Elaborate. 10
(ii) What are the important components that must be considered for implementation of Information Resource Management. 5
(c) (i) Explain the fundamental role of Information Systems in business and organisations. 5
(ii) State at least eight evaluation factors for an excellent information system. 10
हिंदी में पढ़ें
4.(a) (i) "संगठन में विशेषज्ञ प्रणाली महत्त्वपूर्ण भूमिका निभाते हैं।" विशेषज्ञ प्रणाली के कम से कम चार लाभ देते हुए इस कथन की विवेचना कीजिए । 10
(ii) उपयुक्त उदाहरणों द्वारा विशेषज्ञ प्रणाली के विभिन्न अवयवों का विस्तार से व्याख्या कीजिए । 10
(b) (i) "सूचना संसाधन प्रबंधन किसी संगठन की एक रणनीतिक योजना होती है।" विस्तार से व्याख्या कीजिए। 10
(ii) सूचना संसाधन प्रबंधन के कार्यान्वयन के लिए कौन से महत्वपूर्ण अवयव हैं जिन पर विचार किया जाना चाहिए ? 5
(c) (i) संगठन और व्यवसाय में सूचना प्रणाली की मौलिक भूमिका को समझाइये। 5
(ii) उत्कृष्ट सूचना प्रणाली के कम से कम आठ मूल्यांकन कारकों का उल्लेख कीजिए। 10
Answer approach & key points
The directive 'discuss' demands a balanced treatment with elaboration and critical examination across all sub-parts. Allocate approximately 40% of effort to part (a) [20 marks] covering expert systems benefits and components with examples; 30% to part (b) [15 marks] on IRM as strategic plan and implementation components; and 30% to part (c) [15 marks] on fundamental roles of IS and evaluation factors. Structure with a brief introduction, systematic part-wise treatment, and a synthesizing conclusion linking information systems to organizational competitiveness.
- Part (a)(i): Four+ benefits of Expert Systems—preservation of expertise, 24/7 availability, consistency in decision-making, and training/learning support—with organizational context
- Part (a)(ii): Five components of Expert Systems—knowledge base, inference engine, user interface, explanation facility, and knowledge acquisition subsystem—each with domain-specific examples
- Part (b)(i): IRM as strategic plan—alignment with business objectives, resource optimization, competitive advantage, and governance framework
- Part (b)(ii): Implementation components—top management commitment, IT infrastructure, human resource development, change management, and performance metrics
- Part (c)(i): Fundamental roles of IS—operational efficiency, decision support, strategic management, and communication/coordination
- Part (c)(ii): Eight evaluation factors—reliability, timeliness, accuracy, completeness, relevance, usability, security, and cost-effectiveness